Pagpepresyo ng bill of quantities sa praktika: GB/T 50500-2024 (China)
You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.
Kathang-isip na proyekto- Building
- Teaching block, three-storey concrete frame
- Pricing
- Bill of quantities, GB/T 50500-2024
- Contract
- Unit-price contract after a public tender
- Trabaho sa ERP
- 5 gawain, mga 3 oras 40 min
Sino ang nagbibigay ng ano kanino
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dumarating sa iyo
- Tender documentsBill, norms, contract terms
- Norm quantities and pricesGawain 1
- Measures and the safety fee rateGawain 2
- Fee and VAT termsGawain 3
- A colleagueDrafted payment 1
- Draft with the bases swappedGawain 4
Supervising engineer (监理)Verifies quantities and progress- Work measured in period 1Gawain 4
- Re-measured quantitiesGawain 5
IkawCost estimator (造价员), contractorLumalabas sa iyo
- The priced bidGawain 3
- Progress payment 1Gawain 4
- Rate adjustment for two itemsGawain 5
County Education BureauEmployer, pays
Kathang-isip ang proyekto at ang mga tao. Gawa ng computer ang mga larawan.
Ang ruta mo sa proyekto
Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.
Bid
Gawain 1 · 45 min
Composite unit rate: mga beam at haligi
- Ang gagawin mo
- All-in unit rates (综合单价) for beams and columns
- Dokumento
- Norm quantities, prices with VAT, fee rates
- Sa ERP
- Bill of Quantities
Bid
Gawain 2 · 40 min
Mga sinukat na gawain at mga measure
- Ang gagawin mo
- Measures items (temporary works such as scaffold) and the work-safety measures fee
- Dokumento
- Scaffold and formwork rates, the fee's base
- Sa ERP
- Bill of Quantities
Bid
Gawain 3 · 40 min
VAT sa tatlong seksyon
- Ang gagawin mo
- VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
- Dokumento
- The contract's pricing and tax terms, a colleague's draft
- Sa ERP
- Bill of Quantities › Markups
Payment
Gawain 4 · 50 min
Interim payment at pagbawi ng advance
- Ang gagawin mo
- Advance recovery and the amount payable for period 1
- Dokumento
- A colleague's draft and the contract terms
- Sa ERP
- Contracts › Progress Claims
Review
Gawain 5 · 45 min
Paglihis sa dami na higit sa 15 %
- Ang gagawin mo
- Adjusted rates and the variation amount
- Dokumento
- Quantities re-measured after completion
- Sa ERP
- Variations
Every charge on its own base
The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.
Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.
Sa madaling salita. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.