OpenConstruction Academy
Sign in / Register
EN

Course introduction · 3 min

Bill-of-quantities pricing in practice: GB/T 50500-2024 (China)

You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.

Start task 1

A three-storey concrete frame wrapped in green safety netting, a tower crane above it and blue hoarding round the site, with low town houses and hills behind.Fictional project
Yunshan County Experimental Primary SchoolThree-storey frame teaching block · public tender
Building
Teaching block, three-storey concrete frame
Pricing
Bill of quantities, GB/T 50500-2024
Contract
Unit-price contract after a public tender
Work in the ERP
5 tasks, about 3 h 40 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Tender documentsBill, norms, contract terms
    • Norm quantities and pricesTask 1
    • Measures and the safety fee rateTask 2
    • Fee and VAT termsTask 3
  • A colleagueDrafted payment 1
    • Draft with the bases swappedTask 4
  • Supervising engineer (监理)Verifies quantities and progress
    • Work measured in period 1Task 4
    • Re-measured quantitiesTask 5
YouCost estimator (造价员), contractor

Goes from you

    • The priced bidTask 3
    • Progress payment 1Task 4
    • Rate adjustment for two itemsTask 5
    County Education BureauEmployer, pays

The project and the people are fictional. Portraits are generated.

Your route through the job

Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.

  1. Bid

    Task 1 · 45 min

    Composite unit rate: beams and columns

    You produce
    All-in unit rates (综合单价) for beams and columns
    Document
    Norm quantities, prices with VAT, fee rates
    In the ERP
    Bill of Quantities
  2. Bid

    Task 2 · 40 min

    Measured works and measures

    You produce
    Measures items (temporary works such as scaffold) and the work-safety measures fee
    Document
    Scaffold and formwork rates, the fee's base
    In the ERP
    Bill of Quantities
  3. Bid

    Task 3 · 40 min

    VAT on the three sections

    You produce
    VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
    Document
    The contract's pricing and tax terms, a colleague's draft
    In the ERP
    Bill of Quantities › Markups
  4. Payment

    Task 4 · 50 min

    Interim payment and advance recovery

    You produce
    Advance recovery and the amount payable for period 1
    Document
    A colleague's draft and the contract terms
    In the ERP
    Contracts › Progress Claims
  5. Review

    Task 5 · 45 min

    Quantity deviation over 15 %

    You produce
    Adjusted rates and the variation amount
    Document
    Quantities re-measured after completion
    In the ERP
    Variations

Every charge on its own base

The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.

Overhead and profitLabour, materials, plant
Task 1All-in rateNorm quantities, the official labour, material and machine use per unit, times prices net of VAT, then overhead and profit on labour plus plant, not on materials.
Measures and safety feeBill items
Task 2MeasuresScaffold and formwork leave nothing in the building but are priced. The safety fee is a fixed rate on the bill items only.
VATMeasures and safety feeBill items
Task 3VATVAT on the total of all three bill parts, the provisional sum included. No 规费 on top: social insurance is already in the rates.
Retention heldAdvance recoveredPaid this period
Task 4PaymentThe advance is recovered on the value with tax; retention is held on the value without VAT. Swap the bases and both are wrong.

Blue is what the task adds; grey is carried over from before.

In short. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.