Introduksjon til kurset · 3 min
Prising etter mengdefortegnelse i praksis: GB/T 50500-2024 (Kina)
You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.
Fiktivt prosjekt- Building
- Teaching block, three-storey concrete frame
- Pricing
- Bill of quantities, GB/T 50500-2024
- Contract
- Unit-price contract after a public tender
- Arbeid i ERP
- 5 oppgaver, omtrent 3 t 40 min
Hvem gir hva til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til deg
- Tender documentsBill, norms, contract terms
- Norm quantities and pricesOppgave 1
- Measures and the safety fee rateOppgave 2
- Fee and VAT termsOppgave 3
- A colleagueDrafted payment 1
- Draft with the bases swappedOppgave 4
Supervising engineer (监理)Verifies quantities and progress- Work measured in period 1Oppgave 4
- Re-measured quantitiesOppgave 5
DuCost estimator (造价员), contractorGår fra deg
- The priced bidOppgave 3
- Progress payment 1Oppgave 4
- Rate adjustment for two itemsOppgave 5
County Education BureauEmployer, pays
Prosjektet og personene er fiktive. Portrettene er genererte.
Din vei gjennom prosjektet
Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.
Bid
Oppgave 1 · 45 min
Sammensatt enhetspris: bjelker og søyler
- Du leverer
- All-in unit rates (综合单价) for beams and columns
- Dokument
- Norm quantities, prices with VAT, fee rates
- I ERP
- Bill of Quantities
Bid
Oppgave 2 · 40 min
Målte arbeider og tiltaksposter
- Du leverer
- Measures items (temporary works such as scaffold) and the work-safety measures fee
- Dokument
- Scaffold and formwork rates, the fee's base
- I ERP
- Bill of Quantities
Bid
Oppgave 3 · 40 min
Mva. på de tre delene
- Du leverer
- VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
- Dokument
- The contract's pricing and tax terms, a colleague's draft
- I ERP
- Bill of Quantities › Markups
Payment
Oppgave 4 · 50 min
Delbetaling og forskuddsavregning
- Du leverer
- Advance recovery and the amount payable for period 1
- Dokument
- A colleague's draft and the contract terms
- I ERP
- Contracts › Progress Claims
Review
Oppgave 5 · 45 min
Mengdeavvik over 15 %
- Du leverer
- Adjusted rates and the variation amount
- Dokument
- Quantities re-measured after completion
- I ERP
- Variations
Every charge on its own base
The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.
Blått er det oppgaven legger til; grått er overført fra før.
Kort sagt. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.