מבוא לקורס · 3 דק׳
תמחור מעשי לפי כתב כמויות: GB/T 50500-2024 (סין)
You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.
פרויקט בדיוני- Building
- Teaching block, three-storey concrete frame
- Pricing
- Bill of quantities, GB/T 50500-2024
- Contract
- Unit-price contract after a public tender
- עבודה ב-ERP
- 5 משימות, כ-3 ש׳ 40 דק׳
מי מעביר מה למי
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
מגיע אליכם
- Tender documentsBill, norms, contract terms
- Norm quantities and pricesמשימה 1
- Measures and the safety fee rateמשימה 2
- Fee and VAT termsמשימה 3
- A colleagueDrafted payment 1
- Draft with the bases swappedמשימה 4
Supervising engineer (监理)Verifies quantities and progress- Work measured in period 1משימה 4
- Re-measured quantitiesמשימה 5
אתםCost estimator (造价员), contractorיוצא מכם
- The priced bidמשימה 3
- Progress payment 1משימה 4
- Rate adjustment for two itemsמשימה 5
County Education BureauEmployer, pays
הפרויקט והאנשים בדיוניים. הדיוקנאות נוצרו בתוכנה.
המסלול שלכם בפרויקט
Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.
Bid
משימה 1 · 45 דק׳
תעריף יחידה כולל: קורות ועמודים
- התוצר שלכם
- All-in unit rates (综合单价) for beams and columns
- מסמך
- Norm quantities, prices with VAT, fee rates
- ב-ERP
- Bill of Quantities
Bid
משימה 2 · 40 דק׳
עבודות נמדדות ואמצעים נלווים
- התוצר שלכם
- Measures items (temporary works such as scaffold) and the work-safety measures fee
- מסמך
- Scaffold and formwork rates, the fee's base
- ב-ERP
- Bill of Quantities
Bid
משימה 3 · 40 דק׳
מע״מ על שלושת החלקים
- התוצר שלכם
- VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
- מסמך
- The contract's pricing and tax terms, a colleague's draft
- ב-ERP
- Bill of Quantities › Markups
Payment
משימה 4 · 50 דק׳
חשבון ביניים וקיזוז מקדמה
- התוצר שלכם
- Advance recovery and the amount payable for period 1
- מסמך
- A colleague's draft and the contract terms
- ב-ERP
- Contracts › Progress Claims
Review
משימה 5 · 45 דק׳
חריגת כמויות מעל 15 %
- התוצר שלכם
- Adjusted rates and the variation amount
- מסמך
- Quantities re-measured after completion
- ב-ERP
- Variations
Every charge on its own base
The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.
בכחול מה שהמשימה מוסיפה; באפור מה שעבר מהשלב הקודם.
בקצרה. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.