Ажил материалын жагсаалтаар үнэлэх практик: GB/T 50500-2024 (Хятад)

You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.

1-р даалгаврыг эхлэх

A three-storey concrete frame wrapped in green safety netting, a tower crane above it and blue hoarding round the site, with low town houses and hills behind.Зохиомол төсөл
Yunshan County Experimental Primary SchoolThree-storey frame teaching block · public tender
Building
Teaching block, three-storey concrete frame
Pricing
Bill of quantities, GB/T 50500-2024
Contract
Unit-price contract after a public tender
ERP дээрх ажил
Даалгавар: 5, ойролцоогоор 3 цаг 40 мин

Хэн хэнд юу дамжуулдаг

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Танд ирдэг

  • Tender documentsBill, norms, contract terms
    • Norm quantities and pricesДаалгавар 1
    • Measures and the safety fee rateДаалгавар 2
    • Fee and VAT termsДаалгавар 3
  • A colleagueDrafted payment 1
    • Draft with the bases swappedДаалгавар 4
  • Supervising engineer (监理)Verifies quantities and progress
    • Work measured in period 1Даалгавар 4
    • Re-measured quantitiesДаалгавар 5
ТаCost estimator (造价员), contractor

Танаас гардаг

    • The priced bidДаалгавар 3
    • Progress payment 1Даалгавар 4
    • Rate adjustment for two itemsДаалгавар 5
    County Education BureauEmployer, pays

Төсөл ба хүмүүс зохиомол. Хөрөг зургууд үүсгэгдсэн.

Төслөөр явах таны зам

Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.

  1. Bid

    Даалгавар 1 · 45 мин

    Нэгдсэн нэгж үнэ: дам ба багана

    Үр дүн
    All-in unit rates (综合单价) for beams and columns
    Баримт бичиг
    Norm quantities, prices with VAT, fee rates
    ERP дээр
    Bill of Quantities
  2. Bid

    Даалгавар 2 · 40 мин

    Хэмжигдсэн ажил ба арга хэмжээний ажил

    Үр дүн
    Measures items (temporary works such as scaffold) and the work-safety measures fee
    Баримт бичиг
    Scaffold and formwork rates, the fee's base
    ERP дээр
    Bill of Quantities
  3. Bid

    Даалгавар 3 · 40 мин

    Гурван хэсэг дээрх НӨАТ

    Үр дүн
    VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
    Баримт бичиг
    The contract's pricing and tax terms, a colleague's draft
    ERP дээр
    Bill of Quantities › Markups
  4. Payment

    Даалгавар 4 · 50 мин

    Завсрын төлбөр ба урьдчилгаа суутгах

    Үр дүн
    Advance recovery and the amount payable for period 1
    Баримт бичиг
    A colleague's draft and the contract terms
    ERP дээр
    Contracts › Progress Claims
  5. Review

    Даалгавар 5 · 45 мин

    15 %-иас илүү хэмжээний хазайлт

    Үр дүн
    Adjusted rates and the variation amount
    Баримт бичиг
    Quantities re-measured after completion
    ERP дээр
    Variations

Every charge on its own base

The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.

Overhead and profitLabour, materials, plant
Даалгавар 1All-in rateNorm quantities, the official labour, material and machine use per unit, times prices net of VAT, then overhead and profit on labour plus plant, not on materials.
Measures and safety feeBill items
Даалгавар 2MeasuresScaffold and formwork leave nothing in the building but are priced. The safety fee is a fixed rate on the bill items only.
VATMeasures and safety feeBill items
Даалгавар 3VATVAT on the total of all three bill parts, the provisional sum included. No 规费 on top: social insurance is already in the rates.
Retention heldAdvance recoveredPaid this period
Даалгавар 4PaymentThe advance is recovered on the value with tax; retention is held on the value without VAT. Swap the bases and both are wrong.

Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.

Товчхондоо. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.