Úvod do kurzu · 3 min
Oceňování podle rozpočtu v praxi: GB/T 50500-2024 (Čína)
You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.
Smyšlený projekt- Building
- Teaching block, three-storey concrete frame
- Pricing
- Bill of quantities, GB/T 50500-2024
- Contract
- Unit-price contract after a public tender
- Práce v ERP
- Úlohy: 5, asi 3 h 40 min
Kdo komu co předává
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Přichází k vám
- Tender documentsBill, norms, contract terms
- Norm quantities and pricesÚloha 1
- Measures and the safety fee rateÚloha 2
- Fee and VAT termsÚloha 3
- A colleagueDrafted payment 1
- Draft with the bases swappedÚloha 4
Supervising engineer (监理)Verifies quantities and progress- Work measured in period 1Úloha 4
- Re-measured quantitiesÚloha 5
VyCost estimator (造价员), contractorOdchází od vás
- The priced bidÚloha 3
- Progress payment 1Úloha 4
- Rate adjustment for two itemsÚloha 5
County Education BureauEmployer, pays
Projekt i lidé jsou smyšlení. Portréty jsou vygenerované.
Vaše cesta zakázkou
Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.
Bid
Úloha 1 · 45 min
Komplexní jednotková cena: průvlaky a sloupy
- Výstup
- All-in unit rates (综合单价) for beams and columns
- Dokument
- Norm quantities, prices with VAT, fee rates
- V ERP
- Bill of Quantities
Bid
Úloha 2 · 40 min
Měřené práce a opatření
- Výstup
- Measures items (temporary works such as scaffold) and the work-safety measures fee
- Dokument
- Scaffold and formwork rates, the fee's base
- V ERP
- Bill of Quantities
Bid
Úloha 3 · 40 min
DPH ze tří oddílů
- Výstup
- VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
- Dokument
- The contract's pricing and tax terms, a colleague's draft
- V ERP
- Bill of Quantities › Markups
Payment
Úloha 4 · 50 min
Průběžná platba a zúčtování zálohy
- Výstup
- Advance recovery and the amount payable for period 1
- Dokument
- A colleague's draft and the contract terms
- V ERP
- Contracts › Progress Claims
Review
Úloha 5 · 45 min
Odchylka množství nad 15 %
- Výstup
- Adjusted rates and the variation amount
- Dokument
- Quantities re-measured after completion
- V ERP
- Variations
Every charge on its own base
The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.
Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.
Stručně. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.