Курсқа кіріспе · 3 мин
Көлемдер ведомосі бойынша баға қою тәжірибеде: GB/T 50500-2024 (Қытай)
You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.
Ойдан шығарылған жоба- Building
- Teaching block, three-storey concrete frame
- Pricing
- Bill of quantities, GB/T 50500-2024
- Contract
- Unit-price contract after a public tender
- ERP-дегі жұмыс
- Тапсырмалар: 5, шамамен 3 сағ 40 мин
Кім кімге не береді
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Сізге келеді
- Tender documentsBill, norms, contract terms
- Norm quantities and prices1-тапсырма
- Measures and the safety fee rate2-тапсырма
- Fee and VAT terms3-тапсырма
- A colleagueDrafted payment 1
- Draft with the bases swapped4-тапсырма
Supervising engineer (监理)Verifies quantities and progress- Work measured in period 14-тапсырма
- Re-measured quantities5-тапсырма
СізCost estimator (造价员), contractorСізден кетеді
- The priced bid3-тапсырма
- Progress payment 14-тапсырма
- Rate adjustment for two items5-тапсырма
County Education BureauEmployer, pays
Жоба мен адамдар ойдан шығарылған. Портреттер генерацияланған.
Жоба бойынша жолыңыз
Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.
Bid
1-тапсырма · 45 мин
Кешенді бірлік бағасы: арқалықтар мен бағаналар
- Нәтиже
- All-in unit rates (综合单价) for beams and columns
- Құжат
- Norm quantities, prices with VAT, fee rates
- ERP-де
- Bill of Quantities
Bid
2-тапсырма · 40 мин
Өлшенетін жұмыстар және шаралар
- Нәтиже
- Measures items (temporary works such as scaffold) and the work-safety measures fee
- Құжат
- Scaffold and formwork rates, the fee's base
- ERP-де
- Bill of Quantities
Bid
3-тапсырма · 40 мин
Үш бөліктің ҚҚС-ы
- Нәтиже
- VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
- Құжат
- The contract's pricing and tax terms, a colleague's draft
- ERP-де
- Bill of Quantities › Markups
Payment
4-тапсырма · 50 мин
Аралық төлем және аванс ұстау
- Нәтиже
- Advance recovery and the amount payable for period 1
- Құжат
- A colleague's draft and the contract terms
- ERP-де
- Contracts › Progress Claims
Review
5-тапсырма · 45 мин
15 %-дан асатын көлем ауытқуы
- Нәтиже
- Adjusted rates and the variation amount
- Құжат
- Quantities re-measured after completion
- ERP-де
- Variations
Every charge on its own base
The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.
Көкпен — тапсырма қосатын бөлік; сұрмен — алдыңғы қадамнан келгені.
Қысқаша. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.