Көлемдер ведомосі бойынша баға қою тәжірибеде: GB/T 50500-2024 (Қытай)

You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.

1-тапсырманы бастау

A three-storey concrete frame wrapped in green safety netting, a tower crane above it and blue hoarding round the site, with low town houses and hills behind.Ойдан шығарылған жоба
Yunshan County Experimental Primary SchoolThree-storey frame teaching block · public tender
Building
Teaching block, three-storey concrete frame
Pricing
Bill of quantities, GB/T 50500-2024
Contract
Unit-price contract after a public tender
ERP-дегі жұмыс
Тапсырмалар: 5, шамамен 3 сағ 40 мин

Кім кімге не береді

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сізге келеді

  • Tender documentsBill, norms, contract terms
    • Norm quantities and prices1-тапсырма
    • Measures and the safety fee rate2-тапсырма
    • Fee and VAT terms3-тапсырма
  • A colleagueDrafted payment 1
    • Draft with the bases swapped4-тапсырма
  • Supervising engineer (监理)Verifies quantities and progress
    • Work measured in period 14-тапсырма
    • Re-measured quantities5-тапсырма
СізCost estimator (造价员), contractor

Сізден кетеді

    • The priced bid3-тапсырма
    • Progress payment 14-тапсырма
    • Rate adjustment for two items5-тапсырма
    County Education BureauEmployer, pays

Жоба мен адамдар ойдан шығарылған. Портреттер генерацияланған.

Жоба бойынша жолыңыз

Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.

  1. Bid

    1-тапсырма · 45 мин

    Кешенді бірлік бағасы: арқалықтар мен бағаналар

    Нәтиже
    All-in unit rates (综合单价) for beams and columns
    Құжат
    Norm quantities, prices with VAT, fee rates
    ERP-де
    Bill of Quantities
  2. Bid

    2-тапсырма · 40 мин

    Өлшенетін жұмыстар және шаралар

    Нәтиже
    Measures items (temporary works such as scaffold) and the work-safety measures fee
    Құжат
    Scaffold and formwork rates, the fee's base
    ERP-де
    Bill of Quantities
  3. Bid

    3-тапсырма · 40 мин

    Үш бөліктің ҚҚС-ы

    Нәтиже
    VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
    Құжат
    The contract's pricing and tax terms, a colleague's draft
    ERP-де
    Bill of Quantities › Markups
  4. Payment

    4-тапсырма · 50 мин

    Аралық төлем және аванс ұстау

    Нәтиже
    Advance recovery and the amount payable for period 1
    Құжат
    A colleague's draft and the contract terms
    ERP-де
    Contracts › Progress Claims
  5. Review

    5-тапсырма · 45 мин

    15 %-дан асатын көлем ауытқуы

    Нәтиже
    Adjusted rates and the variation amount
    Құжат
    Quantities re-measured after completion
    ERP-де
    Variations

Every charge on its own base

The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.

Overhead and profitLabour, materials, plant
1-тапсырмаAll-in rateNorm quantities, the official labour, material and machine use per unit, times prices net of VAT, then overhead and profit on labour plus plant, not on materials.
Measures and safety feeBill items
2-тапсырмаMeasuresScaffold and formwork leave nothing in the building but are priced. The safety fee is a fixed rate on the bill items only.
VATMeasures and safety feeBill items
3-тапсырмаVATVAT on the total of all three bill parts, the provisional sum included. No 规费 on top: social insurance is already in the rates.
Retention heldAdvance recoveredPaid this period
4-тапсырмаPaymentThe advance is recovered on the value with tax; retention is held on the value without VAT. Swap the bases and both are wrong.

Көкпен — тапсырма қосатын бөлік; сұрмен — алдыңғы қадамнан келгені.

Қысқаша. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.