Въведение в курса · 3 мин
Остойностяване по количествена сметка на практика: GB/T 50500-2024 (Китай)
You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.
Измислен проект- Building
- Teaching block, three-storey concrete frame
- Pricing
- Bill of quantities, GB/T 50500-2024
- Contract
- Unit-price contract after a public tender
- Работа в ERP
- Задачи: 5, около 3 ч 40 мин
Кой какво предава на кого
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Идва при вас
- Tender documentsBill, norms, contract terms
- Norm quantities and pricesЗадача 1
- Measures and the safety fee rateЗадача 2
- Fee and VAT termsЗадача 3
- A colleagueDrafted payment 1
- Draft with the bases swappedЗадача 4
Supervising engineer (监理)Verifies quantities and progress- Work measured in period 1Задача 4
- Re-measured quantitiesЗадача 5
ВиеCost estimator (造价员), contractorТръгва от вас
- The priced bidЗадача 3
- Progress payment 1Задача 4
- Rate adjustment for two itemsЗадача 5
County Education BureauEmployer, pays
Проектът и хората са измислени. Портретите са генерирани.
Вашият път през проекта
Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.
Bid
Задача 1 · 45 мин
Комплексна единична цена: греди и колони
- Вашият резултат
- All-in unit rates (综合单价) for beams and columns
- Документ
- Norm quantities, prices with VAT, fee rates
- В ERP
- Bill of Quantities
Bid
Задача 2 · 40 мин
Измерени работи и мерки
- Вашият резултат
- Measures items (temporary works such as scaffold) and the work-safety measures fee
- Документ
- Scaffold and formwork rates, the fee's base
- В ERP
- Bill of Quantities
Bid
Задача 3 · 40 мин
ДДС върху трите раздела
- Вашият резултат
- VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
- Документ
- The contract's pricing and tax terms, a colleague's draft
- В ERP
- Bill of Quantities › Markups
Payment
Задача 4 · 50 мин
Междинно плащане и възстановяване на аванса
- Вашият резултат
- Advance recovery and the amount payable for period 1
- Документ
- A colleague's draft and the contract terms
- В ERP
- Contracts › Progress Claims
Review
Задача 5 · 45 мин
Отклонение в количествата над 15 %
- Вашият резултат
- Adjusted rates and the variation amount
- Документ
- Quantities re-measured after completion
- В ERP
- Variations
Every charge on its own base
The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.
В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.
Накратко. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.