Въведение в курса · 3 мин

Остойностяване по количествена сметка на практика: GB/T 50500-2024 (Китай)

You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.

Започнете задача 1

A three-storey concrete frame wrapped in green safety netting, a tower crane above it and blue hoarding round the site, with low town houses and hills behind.Измислен проект
Yunshan County Experimental Primary SchoolThree-storey frame teaching block · public tender
Building
Teaching block, three-storey concrete frame
Pricing
Bill of quantities, GB/T 50500-2024
Contract
Unit-price contract after a public tender
Работа в ERP
Задачи: 5, около 3 ч 40 мин

Кой какво предава на кого

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Идва при вас

  • Tender documentsBill, norms, contract terms
    • Norm quantities and pricesЗадача 1
    • Measures and the safety fee rateЗадача 2
    • Fee and VAT termsЗадача 3
  • A colleagueDrafted payment 1
    • Draft with the bases swappedЗадача 4
  • Supervising engineer (监理)Verifies quantities and progress
    • Work measured in period 1Задача 4
    • Re-measured quantitiesЗадача 5
ВиеCost estimator (造价员), contractor

Тръгва от вас

    • The priced bidЗадача 3
    • Progress payment 1Задача 4
    • Rate adjustment for two itemsЗадача 5
    County Education BureauEmployer, pays

Проектът и хората са измислени. Портретите са генерирани.

Вашият път през проекта

Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.

  1. Bid

    Задача 1 · 45 мин

    Комплексна единична цена: греди и колони

    Вашият резултат
    All-in unit rates (综合单价) for beams and columns
    Документ
    Norm quantities, prices with VAT, fee rates
    В ERP
    Bill of Quantities
  2. Bid

    Задача 2 · 40 мин

    Измерени работи и мерки

    Вашият резултат
    Measures items (temporary works such as scaffold) and the work-safety measures fee
    Документ
    Scaffold and formwork rates, the fee's base
    В ERP
    Bill of Quantities
  3. Bid

    Задача 3 · 40 мин

    ДДС върху трите раздела

    Вашият резултат
    VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
    Документ
    The contract's pricing and tax terms, a colleague's draft
    В ERP
    Bill of Quantities › Markups
  4. Payment

    Задача 4 · 50 мин

    Междинно плащане и възстановяване на аванса

    Вашият резултат
    Advance recovery and the amount payable for period 1
    Документ
    A colleague's draft and the contract terms
    В ERP
    Contracts › Progress Claims
  5. Review

    Задача 5 · 45 мин

    Отклонение в количествата над 15 %

    Вашият резултат
    Adjusted rates and the variation amount
    Документ
    Quantities re-measured after completion
    В ERP
    Variations

Every charge on its own base

The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.

Overhead and profitLabour, materials, plant
Задача 1All-in rateNorm quantities, the official labour, material and machine use per unit, times prices net of VAT, then overhead and profit on labour plus plant, not on materials.
Measures and safety feeBill items
Задача 2MeasuresScaffold and formwork leave nothing in the building but are priced. The safety fee is a fixed rate on the bill items only.
VATMeasures and safety feeBill items
Задача 3VATVAT on the total of all three bill parts, the provisional sum included. No 规费 on top: social insurance is already in the rates.
Retention heldAdvance recoveredPaid this period
Задача 4PaymentThe advance is recovered on the value with tax; retention is held on the value without VAT. Swap the bases and both are wrong.

В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.

Накратко. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.