Kursuse sissejuhatus · 3 min

Mahutabeli alusel hindamine praktikas: GB/T 50500-2024 (Hiina)

You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.

Alusta ülesannet 1

A three-storey concrete frame wrapped in green safety netting, a tower crane above it and blue hoarding round the site, with low town houses and hills behind.Väljamõeldud projekt
Yunshan County Experimental Primary SchoolThree-storey frame teaching block · public tender
Building
Teaching block, three-storey concrete frame
Pricing
Bill of quantities, GB/T 50500-2024
Contract
Unit-price contract after a public tender
Töö ERP-s
Ülesandeid 5, umbes 3 h 40 min

Kes annab kellele mida

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tuleb sinule

  • Tender documentsBill, norms, contract terms
    • Norm quantities and pricesÜlesanne 1
    • Measures and the safety fee rateÜlesanne 2
    • Fee and VAT termsÜlesanne 3
  • A colleagueDrafted payment 1
    • Draft with the bases swappedÜlesanne 4
  • Supervising engineer (监理)Verifies quantities and progress
    • Work measured in period 1Ülesanne 4
    • Re-measured quantitiesÜlesanne 5
SinaCost estimator (造价员), contractor

Läheb sinult

    • The priced bidÜlesanne 3
    • Progress payment 1Ülesanne 4
    • Rate adjustment for two itemsÜlesanne 5
    County Education BureauEmployer, pays

Projekt ja inimesed on väljamõeldud. Portreed on genereeritud.

Sinu tee läbi projekti

Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.

  1. Bid

    Ülesanne 1 · 45 min

    Koondhind: talad ja sambad

    Sinu tulemus
    All-in unit rates (综合单价) for beams and columns
    Dokument
    Norm quantities, prices with VAT, fee rates
    ERP-s
    Bill of Quantities
  2. Bid

    Ülesanne 2 · 40 min

    Mõõdetud tööd ja abitööd

    Sinu tulemus
    Measures items (temporary works such as scaffold) and the work-safety measures fee
    Dokument
    Scaffold and formwork rates, the fee's base
    ERP-s
    Bill of Quantities
  3. Bid

    Ülesanne 3 · 40 min

    Käibemaks kolmele jaotisele

    Sinu tulemus
    VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
    Dokument
    The contract's pricing and tax terms, a colleague's draft
    ERP-s
    Bill of Quantities › Markups
  4. Payment

    Ülesanne 4 · 50 min

    Vahemakse ja avansi tagasiarvestus

    Sinu tulemus
    Advance recovery and the amount payable for period 1
    Dokument
    A colleague's draft and the contract terms
    ERP-s
    Contracts › Progress Claims
  5. Review

    Ülesanne 5 · 45 min

    Koguste kõrvalekalle üle 15 %

    Sinu tulemus
    Adjusted rates and the variation amount
    Dokument
    Quantities re-measured after completion
    ERP-s
    Variations

Every charge on its own base

The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.

Overhead and profitLabour, materials, plant
Ülesanne 1All-in rateNorm quantities, the official labour, material and machine use per unit, times prices net of VAT, then overhead and profit on labour plus plant, not on materials.
Measures and safety feeBill items
Ülesanne 2MeasuresScaffold and formwork leave nothing in the building but are priced. The safety fee is a fixed rate on the bill items only.
VATMeasures and safety feeBill items
Ülesanne 3VATVAT on the total of all three bill parts, the provisional sum included. No 规费 on top: social insurance is already in the rates.
Retention heldAdvance recoveredPaid this period
Ülesanne 4PaymentThe advance is recovered on the value with tax; retention is held on the value without VAT. Swap the bases and both are wrong.

Sinine on see, mida ülesanne lisab; hall tuleb varasemast.

Lühidalt. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.