Mahutabeli alusel hindamine praktikas: GB/T 50500-2024 (Hiina)
You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.
Väljamõeldud projekt- Building
- Teaching block, three-storey concrete frame
- Pricing
- Bill of quantities, GB/T 50500-2024
- Contract
- Unit-price contract after a public tender
- Töö ERP-s
- Ülesandeid 5, umbes 3 h 40 min
Kes annab kellele mida
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tuleb sinule
- Tender documentsBill, norms, contract terms
- Norm quantities and pricesÜlesanne 1
- Measures and the safety fee rateÜlesanne 2
- Fee and VAT termsÜlesanne 3
- A colleagueDrafted payment 1
- Draft with the bases swappedÜlesanne 4
Supervising engineer (监理)Verifies quantities and progress- Work measured in period 1Ülesanne 4
- Re-measured quantitiesÜlesanne 5
SinaCost estimator (造价员), contractorLäheb sinult
- The priced bidÜlesanne 3
- Progress payment 1Ülesanne 4
- Rate adjustment for two itemsÜlesanne 5
County Education BureauEmployer, pays
Projekt ja inimesed on väljamõeldud. Portreed on genereeritud.
Sinu tee läbi projekti
Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.
Bid
Ülesanne 1 · 45 min
Koondhind: talad ja sambad
- Sinu tulemus
- All-in unit rates (综合单价) for beams and columns
- Dokument
- Norm quantities, prices with VAT, fee rates
- ERP-s
- Bill of Quantities
Bid
Ülesanne 2 · 40 min
Mõõdetud tööd ja abitööd
- Sinu tulemus
- Measures items (temporary works such as scaffold) and the work-safety measures fee
- Dokument
- Scaffold and formwork rates, the fee's base
- ERP-s
- Bill of Quantities
Bid
Ülesanne 3 · 40 min
Käibemaks kolmele jaotisele
- Sinu tulemus
- VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
- Dokument
- The contract's pricing and tax terms, a colleague's draft
- ERP-s
- Bill of Quantities › Markups
Payment
Ülesanne 4 · 50 min
Vahemakse ja avansi tagasiarvestus
- Sinu tulemus
- Advance recovery and the amount payable for period 1
- Dokument
- A colleague's draft and the contract terms
- ERP-s
- Contracts › Progress Claims
Review
Ülesanne 5 · 45 min
Koguste kõrvalekalle üle 15 %
- Sinu tulemus
- Adjusted rates and the variation amount
- Dokument
- Quantities re-measured after completion
- ERP-s
- Variations
Every charge on its own base
The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.