کورس کا تعارف · 3 منٹ

بل آف کوانٹیٹیز کے مطابق قیمت بندی عملی طور پر: GB/T 50500-2024 (چین)

You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.

ٹاسک 1 شروع کریں

A three-storey concrete frame wrapped in green safety netting, a tower crane above it and blue hoarding round the site, with low town houses and hills behind.فرضی پراجیکٹ
Yunshan County Experimental Primary SchoolThree-storey frame teaching block · public tender
Building
Teaching block, three-storey concrete frame
Pricing
Bill of quantities, GB/T 50500-2024
Contract
Unit-price contract after a public tender
ERP میں کام
5 ٹاسک، تقریباً 3 گھنٹے 40 منٹ

کون کس کو کیا دیتا ہے

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

آپ کے پاس آتا ہے

  • Tender documentsBill, norms, contract terms
    • Norm quantities and pricesٹاسک 1
    • Measures and the safety fee rateٹاسک 2
    • Fee and VAT termsٹاسک 3
  • A colleagueDrafted payment 1
    • Draft with the bases swappedٹاسک 4
  • Supervising engineer (监理)Verifies quantities and progress
    • Work measured in period 1ٹاسک 4
    • Re-measured quantitiesٹاسک 5
آپCost estimator (造价员), contractor

آپ سے جاتا ہے

    • The priced bidٹاسک 3
    • Progress payment 1ٹاسک 4
    • Rate adjustment for two itemsٹاسک 5
    County Education BureauEmployer, pays

پراجیکٹ اور لوگ فرضی ہیں۔ تصاویر تیار کردہ ہیں۔

پراجیکٹ میں آپ کا راستہ

Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.

  1. Bid

    ٹاسک 1 · 45 منٹ

    مجموعی اکائی نرخ: بیم اور کالم

    آپ کا نتیجہ
    All-in unit rates (综合单价) for beams and columns
    دستاویز
    Norm quantities, prices with VAT, fee rates
    ERP میں
    Bill of Quantities
  2. Bid

    ٹاسک 2 · 40 منٹ

    ناپے گئے کام اور ضمنی اقدامات

    آپ کا نتیجہ
    Measures items (temporary works such as scaffold) and the work-safety measures fee
    دستاویز
    Scaffold and formwork rates, the fee's base
    ERP میں
    Bill of Quantities
  3. Bid

    ٹاسک 3 · 40 منٹ

    تینوں حصوں پر VAT

    آپ کا نتیجہ
    VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
    دستاویز
    The contract's pricing and tax terms, a colleague's draft
    ERP میں
    Bill of Quantities › Markups
  4. Payment

    ٹاسک 4 · 50 منٹ

    عبوری ادائیگی اور پیشگی کی وصولی

    آپ کا نتیجہ
    Advance recovery and the amount payable for period 1
    دستاویز
    A colleague's draft and the contract terms
    ERP میں
    Contracts › Progress Claims
  5. Review

    ٹاسک 5 · 45 منٹ

    15 % سے زیادہ مقدار کا انحراف

    آپ کا نتیجہ
    Adjusted rates and the variation amount
    دستاویز
    Quantities re-measured after completion
    ERP میں
    Variations

Every charge on its own base

The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.

Overhead and profitLabour, materials, plant
ٹاسک 1All-in rateNorm quantities, the official labour, material and machine use per unit, times prices net of VAT, then overhead and profit on labour plus plant, not on materials.
Measures and safety feeBill items
ٹاسک 2MeasuresScaffold and formwork leave nothing in the building but are priced. The safety fee is a fixed rate on the bill items only.
VATMeasures and safety feeBill items
ٹاسک 3VATVAT on the total of all three bill parts, the provisional sum included. No 规费 on top: social insurance is already in the rates.
Retention heldAdvance recoveredPaid this period
ٹاسک 4PaymentThe advance is recovered on the value with tax; retention is held on the value without VAT. Swap the bases and both are wrong.

نیلا وہ ہے جو ٹاسک شامل کرتا ہے؛ سرمئی پچھلے مرحلے سے آیا ہے۔

مختصراً. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.