Određivanje cijena po troškovniku u praksi: GB/T 50500-2024 (Kina)

You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.

Započni zadatak 1

A three-storey concrete frame wrapped in green safety netting, a tower crane above it and blue hoarding round the site, with low town houses and hills behind.Izmišljeni projekt
Yunshan County Experimental Primary SchoolThree-storey frame teaching block · public tender
Building
Teaching block, three-storey concrete frame
Pricing
Bill of quantities, GB/T 50500-2024
Contract
Unit-price contract after a public tender
Rad u ERP-u
Zadataka: 5, oko 3 h 40 min

Tko kome što predaje

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dolazi vama

  • Tender documentsBill, norms, contract terms
    • Norm quantities and pricesZadatak 1
    • Measures and the safety fee rateZadatak 2
    • Fee and VAT termsZadatak 3
  • A colleagueDrafted payment 1
    • Draft with the bases swappedZadatak 4
  • Supervising engineer (监理)Verifies quantities and progress
    • Work measured in period 1Zadatak 4
    • Re-measured quantitiesZadatak 5
ViCost estimator (造价员), contractor

Odlazi od vas

    • The priced bidZadatak 3
    • Progress payment 1Zadatak 4
    • Rate adjustment for two itemsZadatak 5
    County Education BureauEmployer, pays

Projekt i osobe su izmišljeni. Portreti su generirani.

Vaš put kroz projekt

Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.

  1. Bid

    Zadatak 1 · 45 min

    Složena jedinična cijena: grede i stupovi

    Vaš rezultat
    All-in unit rates (综合单价) for beams and columns
    Dokument
    Norm quantities, prices with VAT, fee rates
    U ERP-u
    Bill of Quantities
  2. Bid

    Zadatak 2 · 40 min

    Izmjereni radovi i pomoćni radovi

    Vaš rezultat
    Measures items (temporary works such as scaffold) and the work-safety measures fee
    Dokument
    Scaffold and formwork rates, the fee's base
    U ERP-u
    Bill of Quantities
  3. Bid

    Zadatak 3 · 40 min

    PDV na tri dijela

    Vaš rezultat
    VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
    Dokument
    The contract's pricing and tax terms, a colleague's draft
    U ERP-u
    Bill of Quantities › Markups
  4. Payment

    Zadatak 4 · 50 min

    Privremena situacija i povrat predujma

    Vaš rezultat
    Advance recovery and the amount payable for period 1
    Dokument
    A colleague's draft and the contract terms
    U ERP-u
    Contracts › Progress Claims
  5. Review

    Zadatak 5 · 45 min

    Odstupanje količina veće od 15 %

    Vaš rezultat
    Adjusted rates and the variation amount
    Dokument
    Quantities re-measured after completion
    U ERP-u
    Variations

Every charge on its own base

The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.

Overhead and profitLabour, materials, plant
Zadatak 1All-in rateNorm quantities, the official labour, material and machine use per unit, times prices net of VAT, then overhead and profit on labour plus plant, not on materials.
Measures and safety feeBill items
Zadatak 2MeasuresScaffold and formwork leave nothing in the building but are priced. The safety fee is a fixed rate on the bill items only.
VATMeasures and safety feeBill items
Zadatak 3VATVAT on the total of all three bill parts, the provisional sum included. No 规费 on top: social insurance is already in the rates.
Retention heldAdvance recoveredPaid this period
Zadatak 4PaymentThe advance is recovered on the value with tax; retention is held on the value without VAT. Swap the bases and both are wrong.

Plavo je ono što zadatak dodaje; sivo se prenosi od prije.

Ukratko. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.