Uvod u tečaj · 3 min
Određivanje cijena po troškovniku u praksi: GB/T 50500-2024 (Kina)
You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.
Izmišljeni projekt- Building
- Teaching block, three-storey concrete frame
- Pricing
- Bill of quantities, GB/T 50500-2024
- Contract
- Unit-price contract after a public tender
- Rad u ERP-u
- Zadataka: 5, oko 3 h 40 min
Tko kome što predaje
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dolazi vama
- Tender documentsBill, norms, contract terms
- Norm quantities and pricesZadatak 1
- Measures and the safety fee rateZadatak 2
- Fee and VAT termsZadatak 3
- A colleagueDrafted payment 1
- Draft with the bases swappedZadatak 4
Supervising engineer (监理)Verifies quantities and progress- Work measured in period 1Zadatak 4
- Re-measured quantitiesZadatak 5
ViCost estimator (造价员), contractorOdlazi od vas
- The priced bidZadatak 3
- Progress payment 1Zadatak 4
- Rate adjustment for two itemsZadatak 5
County Education BureauEmployer, pays
Projekt i osobe su izmišljeni. Portreti su generirani.
Vaš put kroz projekt
Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.
Bid
Zadatak 1 · 45 min
Složena jedinična cijena: grede i stupovi
- Vaš rezultat
- All-in unit rates (综合单价) for beams and columns
- Dokument
- Norm quantities, prices with VAT, fee rates
- U ERP-u
- Bill of Quantities
Bid
Zadatak 2 · 40 min
Izmjereni radovi i pomoćni radovi
- Vaš rezultat
- Measures items (temporary works such as scaffold) and the work-safety measures fee
- Dokument
- Scaffold and formwork rates, the fee's base
- U ERP-u
- Bill of Quantities
Bid
Zadatak 3 · 40 min
PDV na tri dijela
- Vaš rezultat
- VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
- Dokument
- The contract's pricing and tax terms, a colleague's draft
- U ERP-u
- Bill of Quantities › Markups
Payment
Zadatak 4 · 50 min
Privremena situacija i povrat predujma
- Vaš rezultat
- Advance recovery and the amount payable for period 1
- Dokument
- A colleague's draft and the contract terms
- U ERP-u
- Contracts › Progress Claims
Review
Zadatak 5 · 45 min
Odstupanje količina veće od 15 %
- Vaš rezultat
- Adjusted rates and the variation amount
- Dokument
- Quantities re-measured after completion
- U ERP-u
- Variations
Every charge on its own base
The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.