Kurssin johdanto · 3 min

Määräluettelon mukainen hinnoittelu käytännössä: GB/T 50500-2024 (Kiina)

You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.

Aloita tehtävä 1

A three-storey concrete frame wrapped in green safety netting, a tower crane above it and blue hoarding round the site, with low town houses and hills behind.Kuvitteellinen hanke
Yunshan County Experimental Primary SchoolThree-storey frame teaching block · public tender
Building
Teaching block, three-storey concrete frame
Pricing
Bill of quantities, GB/T 50500-2024
Contract
Unit-price contract after a public tender
Työ ERP:ssä
Tehtäviä 5, noin 3 t 40 min

Kuka antaa mitä kenelle

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tulee sinulle

  • Tender documentsBill, norms, contract terms
    • Norm quantities and pricesTehtävä 1
    • Measures and the safety fee rateTehtävä 2
    • Fee and VAT termsTehtävä 3
  • A colleagueDrafted payment 1
    • Draft with the bases swappedTehtävä 4
  • Supervising engineer (监理)Verifies quantities and progress
    • Work measured in period 1Tehtävä 4
    • Re-measured quantitiesTehtävä 5
SinäCost estimator (造价员), contractor

Lähtee sinulta

    • The priced bidTehtävä 3
    • Progress payment 1Tehtävä 4
    • Rate adjustment for two itemsTehtävä 5
    County Education BureauEmployer, pays

Hanke ja henkilöt ovat kuvitteellisia. Muotokuvat on luotu tekoälyllä.

Reittisi hankkeen läpi

Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.

  1. Bid

    Tehtävä 1 · 45 min

    Yhdistetty yksikköhinta: palkit ja pilarit

    Tuotat
    All-in unit rates (综合单价) for beams and columns
    Asiakirja
    Norm quantities, prices with VAT, fee rates
    ERP:ssä
    Bill of Quantities
  2. Bid

    Tehtävä 2 · 40 min

    Mitatut työt ja toimenpiteet

    Tuotat
    Measures items (temporary works such as scaffold) and the work-safety measures fee
    Asiakirja
    Scaffold and formwork rates, the fee's base
    ERP:ssä
    Bill of Quantities
  3. Bid

    Tehtävä 3 · 40 min

    Arvonlisävero kolmesta osiosta

    Tuotat
    VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
    Asiakirja
    The contract's pricing and tax terms, a colleague's draft
    ERP:ssä
    Bill of Quantities › Markups
  4. Payment

    Tehtävä 4 · 50 min

    Erämaksu ja ennakon palautus

    Tuotat
    Advance recovery and the amount payable for period 1
    Asiakirja
    A colleague's draft and the contract terms
    ERP:ssä
    Contracts › Progress Claims
  5. Review

    Tehtävä 5 · 45 min

    Yli 15 %:n määräpoikkeama

    Tuotat
    Adjusted rates and the variation amount
    Asiakirja
    Quantities re-measured after completion
    ERP:ssä
    Variations

Every charge on its own base

The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.

Overhead and profitLabour, materials, plant
Tehtävä 1All-in rateNorm quantities, the official labour, material and machine use per unit, times prices net of VAT, then overhead and profit on labour plus plant, not on materials.
Measures and safety feeBill items
Tehtävä 2MeasuresScaffold and formwork leave nothing in the building but are priced. The safety fee is a fixed rate on the bill items only.
VATMeasures and safety feeBill items
Tehtävä 3VATVAT on the total of all three bill parts, the provisional sum included. No 规费 on top: social insurance is already in the rates.
Retention heldAdvance recoveredPaid this period
Tehtävä 4PaymentThe advance is recovered on the value with tax; retention is held on the value without VAT. Swap the bases and both are wrong.

Sininen on se, mitä tehtävä lisää; harmaa tulee aiemmasta.

Lyhyesti. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.