Kurssin johdanto · 3 min
Määräluettelon mukainen hinnoittelu käytännössä: GB/T 50500-2024 (Kiina)
You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.
Kuvitteellinen hanke- Building
- Teaching block, three-storey concrete frame
- Pricing
- Bill of quantities, GB/T 50500-2024
- Contract
- Unit-price contract after a public tender
- Työ ERP:ssä
- Tehtäviä 5, noin 3 t 40 min
Kuka antaa mitä kenelle
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tulee sinulle
- Tender documentsBill, norms, contract terms
- Norm quantities and pricesTehtävä 1
- Measures and the safety fee rateTehtävä 2
- Fee and VAT termsTehtävä 3
- A colleagueDrafted payment 1
- Draft with the bases swappedTehtävä 4
Supervising engineer (监理)Verifies quantities and progress- Work measured in period 1Tehtävä 4
- Re-measured quantitiesTehtävä 5
SinäCost estimator (造价员), contractorLähtee sinulta
- The priced bidTehtävä 3
- Progress payment 1Tehtävä 4
- Rate adjustment for two itemsTehtävä 5
County Education BureauEmployer, pays
Hanke ja henkilöt ovat kuvitteellisia. Muotokuvat on luotu tekoälyllä.
Reittisi hankkeen läpi
Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.
Bid
Tehtävä 1 · 45 min
Yhdistetty yksikköhinta: palkit ja pilarit
- Tuotat
- All-in unit rates (综合单价) for beams and columns
- Asiakirja
- Norm quantities, prices with VAT, fee rates
- ERP:ssä
- Bill of Quantities
Bid
Tehtävä 2 · 40 min
Mitatut työt ja toimenpiteet
- Tuotat
- Measures items (temporary works such as scaffold) and the work-safety measures fee
- Asiakirja
- Scaffold and formwork rates, the fee's base
- ERP:ssä
- Bill of Quantities
Bid
Tehtävä 3 · 40 min
Arvonlisävero kolmesta osiosta
- Tuotat
- VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
- Asiakirja
- The contract's pricing and tax terms, a colleague's draft
- ERP:ssä
- Bill of Quantities › Markups
Payment
Tehtävä 4 · 50 min
Erämaksu ja ennakon palautus
- Tuotat
- Advance recovery and the amount payable for period 1
- Asiakirja
- A colleague's draft and the contract terms
- ERP:ssä
- Contracts › Progress Claims
Review
Tehtävä 5 · 45 min
Yli 15 %:n määräpoikkeama
- Tuotat
- Adjusted rates and the variation amount
- Asiakirja
- Quantities re-measured after completion
- ERP:ssä
- Variations
Every charge on its own base
The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.
Sininen on se, mitä tehtävä lisää; harmaa tulee aiemmasta.
Lyhyesti. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.