Introduktion til kurset · 3 min
Prissætning efter tilbudsliste i praksis: GB/T 50500-2024 (Kina)
You are the contractor's cost estimator (造价员) on a county primary school in China: you work out the price the builder bids and what it is paid. In five tasks you build the bid from all-in unit rates to VAT, draw the first progress payment and reprice two items whose quantities moved past the limit the contract allows. The rules come from GB/T 50500-2024, China's national standard for pricing with a bill of quantities.
Fiktivt projekt- Building
- Teaching block, three-storey concrete frame
- Pricing
- Bill of quantities, GB/T 50500-2024
- Contract
- Unit-price contract after a public tender
- Arbejde i ERP
- 5 opgaver, cirka 3 t 40 min
Hvem giver hvad til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til dig
- Tender documentsBill, norms, contract terms
- Norm quantities and pricesOpgave 1
- Measures and the safety fee rateOpgave 2
- Fee and VAT termsOpgave 3
- A colleagueDrafted payment 1
- Draft with the bases swappedOpgave 4
Supervising engineer (监理)Verifies quantities and progress- Work measured in period 1Opgave 4
- Re-measured quantitiesOpgave 5
DigCost estimator (造价员), contractorGår fra dig
- The priced bidOpgave 3
- Progress payment 1Opgave 4
- Rate adjustment for two itemsOpgave 5
County Education BureauEmployer, pays
Projektet og personerne er fiktive. Portrætterne er genererede.
Din vej gennem sagen
Three tasks price the bid in March, one draws the first payment in August, one reprices quantities at the December review. Each works on the same bill. Start with task 1: in the Bill of Quantities you build the all-in unit rates for beams and columns.
Bid
Opgave 1 · 45 min
Sammensat enhedspris: bjælker og søjler
- Du leverer
- All-in unit rates (综合单价) for beams and columns
- Dokument
- Norm quantities, prices with VAT, fee rates
- I ERP
- Bill of Quantities
Bid
Opgave 2 · 40 min
Målte arbejder og foranstaltninger
- Du leverer
- Measures items (temporary works such as scaffold) and the work-safety measures fee
- Dokument
- Scaffold and formwork rates, the fee's base
- I ERP
- Bill of Quantities
Bid
Opgave 3 · 40 min
Moms på de tre afsnit
- Du leverer
- VAT on the three bill parts as a markup, with no separate 规费 (fees set by the government)
- Dokument
- The contract's pricing and tax terms, a colleague's draft
- I ERP
- Bill of Quantities › Markups
Payment
Opgave 4 · 50 min
Aconto-betaling og forskudsmodregning
- Du leverer
- Advance recovery and the amount payable for period 1
- Dokument
- A colleague's draft and the contract terms
- I ERP
- Contracts › Progress Claims
Review
Opgave 5 · 45 min
Mængdeafvigelse over 15 %
- Du leverer
- Adjusted rates and the variation amount
- Dokument
- Quantities re-measured after completion
- I ERP
- Variations
Every charge on its own base
The first three bars are the bid as it grows, one task at a time. The fourth is one period of work, split into what is paid and what is kept.
Blå er det, opgaven tilføjer; grå er overført fra før.
Kort sagt. Price net of VAT, put each fee on the base the contract names, and never swap the bases of advance recovery and retention.