OpenConstruction Academy
Logi sisse / Registreeru
ET

Teooria enne ülesannet 2 · 9 min

Holdback and HST: what the owner actually pays

Pidatis, HST ja mis tegelikult makstakse

Pärast seda loengut oskad

  1. State the Ontario statutory holdback and what it is calculated on.
  2. Work from the value of a claim to the amount payable now, HST included.
  3. Keep a running total of the holdback the owner is holding.
1 / 3

Why the owner holds money back

Under Ontario's Construction Act, s. 22 (1), every payer on a contract under which a lien may arise retains a holdback of 10 per cent of the price of the services or materials as they are supplied. The money protects subcontractors and suppliers further down: if the contractor fails to pay them, they can lien the land, and the holdback is the owner's fund to answer those liens. It is not a penalty and not a retention for defects; it is released once the lien period has run out.

Näide. On a claim of $412,000.00 the owner keeps $41,200.00 and pays on $370,800.00.
Value of the claim, excluding HST$412,000.00
Holdback$41,200.00
Net for payment now$370,800.00
2 / 3

HST follows the money

Ontario HST is 13 per cent: 5 per cent federal and 8 per cent provincial (Excise Tax Act, s. 165). Under s. 168 (7), tax on a construction holdback becomes payable only when the holdback is paid or becomes payable. So the invoice charges HST on the net amount paid now, and the tax on the holdback waits for its release. Charging HST on the full claim and then deducting the holdback overstates what is due today.

Näide. Net $370,800.00 × 1.13 = $419,004.00 payable now.
3 / 3

The holdback accumulates

Each claim adds 10 per cent of its value to the fund. After any claim the owner holds 10 per cent of everything certified so far, excluding HST. Keeping that running total right matters at the end: it is the amount released at substantial performance, and the amount subcontractors look to if they are not paid.

$118,000$41,200
  • Holdback on earlier claims $118,000
  • Holdback on this claim $41,200

From claim value to cheque

A contractor's claim on an Ontario school addition has been certified. Work out what the owner pays now and what it then holds.

Mõõtkavata
Ülesanne
  • Value of this claim, excluding HST: $412,000.00.
  • Statutory holdback 10%; HST 13% on the net amount paid now.
  • Certified in earlier claims, excluding HST: $1,180,000.00.
Samm 1 / 3

Holdback on the claim

Holdback on the value before tax. What is it?

$412,000.00 × 10% = $41,200.00.

+$412,0001−$41,2002+$48,2043?4
  • 1 Claim
  • 2 Holdback
  • 3 HST on net
  • 4 Payable
+$412,0001−$41,2002+$48,2043$419,0044
  • 1 Claim
  • 2 Holdback
  • 3 HST on net
  • 4 Payable
Samm 2 / 3

Payable now

Net of holdback, plus HST on the net. What does the owner pay now?

($412,000.00 − $41,200.00) × 1.13 = $419,004.00.

Samm 3 / 3

Holdback held

Holdback on everything certified so far. How much does the owner now hold?

($1,180,000.00 + $412,000.00) × 10% = $159,200.00.

Lühidalt. Holdback on the value before tax; HST on the net paid now; the fund grows with each claim.

Kontrolli ennast

Küsimus 1 / 3

A claim is worth $288,000.00 excluding HST. Holdback is 10 % and HST 13 % on the net paid now. What does the owner pay now?

$288,000.00 − $28,800.00 = $259,200.00; × 1.13 = $292,896.00.
Küsimus 2 / 3

Why is HST on the holdback not invoiced with each claim?

  • It is not exempt; the tax is only deferred.

  • Right: Excise Tax Act, s. 168 (7).

  • No. The contractor collects it when the holdback is released.

Küsimus 3 / 3

Who is the holdback mainly there to protect?

  • Defects are dealt with by the contract and warranties, not the statutory holdback.

  • Right. It is the fund that answers their liens.

  • The consultant has no claim on it.