OpenConstruction Academy
Logi sisse / Registreeru
ET

Teooria enne ülesannet 3 · 9 min

Pricing a change: cost, then the agreed allowance

Muudatuskorralduse hindamine juurdehindlustega

Pärast seda loengut oskad

  1. Tell a change directive from a change order under CCDC 2.
  2. Build the own-forces cost of a change from hours, quantities and rates.
  3. Apply the contract's allowances correctly: one rate on own forces, a lower one on a subcontractor's price.
1 / 3

Directive first, price after

CCDC 2 handles changes in Part 6. When owner and contractor agree the price and time of a change, they sign a change order. When the work cannot wait for agreement, the consultant issues a change directive: the contractor proceeds, and the value is settled afterwards from the actual cost plus the allowances the contract fixes. Directives are common below ground, where nobody can price rock before it is found.

Näide. A directive tells you to do the work now; the change order later records what it cost.
2 / 3

Own-forces cost

Own-forces cost is what the contractor itself spends: labour hours × hourly rate, materials × unit rate, plant days × day rate. Count only what the change caused. The Supplementary Conditions usually fix the rates and what counts as cost, so use the contract's rates, not the site's guess.

Carpenters, hours64
Rate per hour$58.40
Labourers, hours80
Rate per hour$47.10
Labour cost$7,505.60
3 / 3

Two allowances, two bases

The contractor's overhead and profit on a change come as an allowance, a percentage the contract fixes in advance. This contract fixes one rate on own-forces cost and a lower one on a subcontractor's price, because the subcontractor's quote already carries the subcontractor's own markup. Apply each rate only to its own base. Putting the own-forces rate on the sublet work, or marking up the total twice, is the common error.

Näide. Sublet price $12,600.00 at 5 %: allowance $630.00, not $1,260.00.

Price a thickened slab edge

On a warehouse the consultant directed a thickened slab edge after soft ground was found. Part of the work, the soil stabilisation, was sublet.

Mõõtkavata
Ülesanne
  • Carpenters 64 h at $58.40; labourers 80 h at $47.10.
  • Concrete 32 m³ at $228.00; reinforcing steel 2,600 kg at $1.72.
  • Stabilisation subcontractor's quoted price, its own markup included: $12,600.00.
  • Allowances: 10% on own-forces cost, 5% on a subcontractor's price.
Samm 1 / 3

Own-forces cost

Labour, concrete and steel. What is the own-forces cost?

64 × $58.40 + 80 × $47.10 + 32 × $228.00 + 2,600 × $1.72 = $19,273.60.

Samm 2 / 3

Allowance on the sublet work

The lower rate on the subcontractor's price. What is it?

$12,600.00 × 5% = $630.00.

$19,274$12,600
  • Own cost $19,274
  • Own allowance $1,927
  • Subcontract $12,600
  • Sublet allowance $630
$19,274$12,600
  • Own cost $19,274
  • Own allowance $1,927
  • Subcontract $12,600
  • Sublet allowance $630
Samm 3 / 3

Value of the change

Own cost with its allowance, plus the sublet price with its allowance. What is the change worth, excluding HST?

$19,273.60 × 1.10 + $12,600.00 + $630.00 = $34,430.96.

Lühidalt. Cost what the change caused; mark up own forces at the own rate and sublet work at the sublet rate, once each.

Kontrolli ennast

Küsimus 1 / 2

A subcontractor quotes $9,800.00 for a change, its markup included. The contract allows 12 % on own forces and 5 % on a subcontractor's price. What allowance does the contractor add?

$9,800.00 × 5 % = $490.00.
Küsimus 2 / 2

The consultant needs rock removed today, before a price can be agreed. What does CCDC 2 use?

  • A change order records an agreed price; there is none yet.

  • Right. The work proceeds and the value is settled from cost plus allowances.

  • Nothing here is about time.