OpenConstruction Academy
ورود / ثبت‌نام
FA

نظریه پیش از تکلیف 3 · 10 دقیقه

Schedule base rates, the station cost index and the tender percentage

قیمت‌گذاری صورت‌ریز: نرخ‌های پایه، شاخص هزینه، درصد پیشنهاد مناقصه

پس از این درس می‌توانید

  1. Price every line of the abstract at the base rate of the schedule, with nothing added.
  2. Add the cost index once, on the base total.
  3. Take the tender percentage on the indexed total, above or below.
1 / 3

Base rates: the schedule, as printed

Central public works in India are estimated from the CPWD Delhi Schedule of Rates (DSR) or a schedule built the same way. Its rates are base rates for the base station and the year of the schedule. The estimate is quantities times those base rates, line by line. In the bill the unit rate of each line is the base rate exactly as the schedule prints it: no index inside it, no percentage inside it.

مثال. 42.50 m³ of concrete at a base rate of ₹6,120.00 per m³ is ₹260,100.00 on the line.
Quantity, m³42.5
Base rate per m³₹6,120.00
Line at base rate₹2,60,100.00
2 / 3

The cost index brings the schedule to the station

Prices in one city are not prices in another. The department notifies a cost index for each station on a base of 100: an index of 109 means 9 % over the base rates. It is applied once, as one line on the total of the schedule items. Put it inside a rate and then add the index line as well, and the index is paid twice.

مثال. ₹500,000.00 at base rates with an index of 109: the index line is ₹45,000.00.
₹5,00,000
  • Abstract at base rates ₹5,00,000
  • Cost index 109, on the base total ₹45,000
3 / 3

The tender percentage sits on top

In a percentage rate tender under the CPWD General Conditions of Contract 2023 the contractor does not price items. He quotes one percentage above or below the estimated cost, and the estimated cost already carries the cost index. So the tender percentage is taken on the indexed total. Adding the two percentages together and applying them once gives a different, wrong figure.

مثال. The order is fixed: base total, then the index on it, then the tender percentage on the indexed total.
Base total₹5,00,000.00
Index 109, then 5 % above₹5,72,250.00
9 % + 5 % added in one step (wrong)₹5,70,000.00

Price the abstract of a hostel block

Another job, another station. Three sections already at base rates; the index is 108 and the contractor quoted 3.75 % below.

بدون مقیاس
مسئله
  • Section 1, earthwork and foundations: ₹1,86,450.00. Section 2, concrete and masonry: ₹5,12,380.00. Section 3, finishing: ₹1,43,270.00. All at base rates.
  • Cost index for the station: 108 on a base of 100.
  • Tender percentage: 3.75 % below the estimated cost.
₹1,86,450₹5,12,380₹1,43,270
  • Section 1 ₹1,86,450
  • Section 2 ₹5,12,380
  • Section 3 ₹1,43,270
₹1,86,450₹5,12,380₹1,43,270
  • Section 1 ₹1,86,450
  • Section 2 ₹5,12,380
  • Section 3 ₹1,43,270
گام 1 از 4

Total at base rates

Add the three sections. What is the abstract at base rates?

₹1,86,450.00 + ₹5,12,380.00 + ₹1,43,270.00 = ₹8,42,100.00.

گام 2 از 4

Cost index line

The index is 108. What is the index line on ₹8,42,100.00?

8 % of ₹8,42,100.00 = ₹67,368.00.

گام 3 از 4

Tender percentage line

3.75 % below, on the indexed total. What is the tender line? It is negative.

(₹8,42,100.00 + ₹67,368.00) × −3.75 % = −₹34,105.05.

₹8,42,1001+₹67,3682−₹34,1053?4
  • 1 Base total
  • 2 Cost index
  • 3 Tender percentage
  • 4 Gross value
₹8,42,1001+₹67,3682−₹34,1053₹8,75,3634
  • 1 Base total
  • 2 Cost index
  • 3 Tender percentage
  • 4 Gross value
گام 4 از 4

Gross value of the abstract

Base total, plus the index line, plus the (negative) tender line. What is the gross?

₹8,42,100.00 + ₹67,368.00 + (−₹34,105.05) = ₹8,75,362.95.

به‌طور خلاصه. Base rates on the lines, the index once on their total, the tender percentage on the indexed total. In the ERP that is two markups: the index on the sum of positions, the tender percentage on the running total including the rows above.

خودتان را بسنجید

پرسش 1 از 3

The schedule's base rate for a line is ₹5,800.00 per m³ and the station index is 115. What goes in the Unit Rate of that line?

  • Right. The index comes later, once, as its own line.

  • Then the index line below adds 15 % a second time.

  • In a percentage rate tender nothing is quoted item by item. The contractor quotes one percentage on the whole.

پرسش 2 از 3

Index 110, tender 5 % below. Which formula gives the gross from the base total B?

  • Right. Index first, then the tender percentage on the indexed total.

  • You netted +10 % and −5 % into one figure. The tender percentage is on the indexed total, not on B.

  • Base rates carry no index. The index line goes on B first, then the tender percentage on B × 1.10.

پرسش 3 از 3

An abstract totals ₹640,000.00 at base rates. The station index is 115 and the tender is 2 % above. What is the gross value?

640,000.00 × 1.15 = 736,000.00; × 1.02 = 750,720.00.