Teoria ennen tehtävää 5 · 8 min

Comparing a cost plan with a budget

Sovita kustannussuunnitelma 2 budjettiin

Tämän luennon jälkeen osaat

  1. Bring a budget that includes VAT, fees and other costs to the same basis as the cost plan.
  2. State a variance with the right sign.
  3. Report the cost per m² GIFA for the cost check.
1 / 4

Two numbers on different bases

The client's budget is everything the project may spend: construction, design fees, other project costs, and VAT the client cannot recover. The cost plan is building works only, without VAT. Before you subtract one from the other, strip the budget down to construction without VAT.

Esimerkki. A budget of £6,000,000 including VAT holds 1,000,000 pounds of VAT and 700,000 pounds of fees and other costs. What is left for building is 4,300,000 pounds.
£1,000,000£4,300,000
  • VAT £1,000,000
  • Design fees £500,000
  • Other project costs £200,000
  • Construction budget £4,300,000
2 / 4

Divide VAT out, do not take it off

A figure that includes 20% VAT is 120% of the net. To find the net, divide by 1.20. Taking 20% off the gross removes too much, because 20% of the gross is larger than 20% of the net.

Esimerkki. From £1,200,000 including VAT, dividing gives 1,000,000 pounds net. Taking 20% off gives 960,000 pounds, which is 40,000 pounds short.
Divided by 1.20
£1,000,000
20% taken off
£960,000
3 / 4

Variance has a sign

Variance is the construction budget less the cost plan. A positive figure is room left in the budget. A negative figure is how far the plan is over. Say which convention you use in the report, and keep it.

Esimerkki. Over budget by 80,000 pounds is reported as a variance of minus 80,000 pounds. The same number without its sign tells the client the opposite.
4 / 4

The cost per m² for the cost check

The client and anyone checking the plan will compare it with other buildings. That comparison is on the cost limit, with preliminaries, risk and inflation in, divided by GIFA, all floors. Fees and other costs stay out, as they do in a benchmark.

Esimerkki. Divided by the footprint the rate looks two or three times too high. Divided by the works before mark-ups it looks too low. Each figure answers a different question; the cost check asks for one.

Reconcile a clinic's cost plan

A different client and different figures. Predict each figure first.

Ei mittakaavassa
Tehtävä
  • Budget £9,600,000, including VAT at 20%, which the client cannot recover.
  • It covers design fees £900,000, other project costs £300,000 and construction.
  • Cost plan, cost limit at the tender date, without VAT: £6,700,000. GIFA 1,200.00 m².
Budget with VAT
£9,600,000
Budget without VAT
?
Budget with VAT
£9,600,000
Budget without VAT
£8,000,000
Vaihe 1/4

Budget without VAT

Take VAT out of the budget. What is left?

£9,600,000 ÷ 1.20 = £8,000,000.

£8,000,0001−£900,0002−£300,0003?4
  • 1 Budget without VAT
  • 2 Fees
  • 3 Other costs
  • 4 Construction budget
£8,000,0001−£900,0002−£300,0003£6,800,0004
  • 1 Budget without VAT
  • 2 Fees
  • 3 Other costs
  • 4 Construction budget
Vaihe 2/4

Construction budget

Take off the fees and the other project costs. What is the construction budget?

£8,000,000 − £900,000 − £300,000 = £6,800,000.

Construction budget
£6,800,000
Cost plan
£6,700,000
Construction budget
£6,800,000
Cost plan
£6,700,000
Vaihe 3/4

Variance

Construction budget less cost plan. What is the variance, with its sign?

£6,800,000 − £6,700,000 = £100,000. The plan is inside the budget.

Cost limit£6,700,000
GIFA1,200.00 m²
Per m² GIFA?
Cost limit£6,700,000
GIFA1,200.00 m²
Per m² GIFA£5,583.33
Vaihe 4/4

Cost per m² GIFA

Cost limit divided by GIFA. Give pence.

£6,700,000 ÷ 1,200.00 m² = £5,583.33 per m² GIFA.

Lyhyesti. Divide VAT out, take fees and other costs off, subtract the plan from what is left, and divide the plan by GIFA for the cost check.

Testaa itsesi

Kysymys 1/3

A budget is £12,000,000 including VAT at 20%. Fees are £1,100,000 and other project costs £400,000. The cost plan is £8,600,000 without VAT. What is the variance (budget less plan)?

£12,000,000 ÷ 1.20 = £10,000,000. Less £1,500,000 of fees and other costs = £8,500,000. Less the plan: −£100,000, over budget.
Kysymys 2/3

Which figure goes into the cost check per m² GIFA?

  • The cost check is on the cost limit, with preliminaries, risk and inflation in.

  • That is the figure a benchmark is comparable with.

  • The budget includes fees, other costs and VAT that no building benchmark carries.

Kysymys 3/3

The value engineering option has been accepted. Which cost plan do you report against the budget?

  • It is out of date. Report the plan that reflects the current design.

  • The report is about the design the client has chosen.

  • That was the concept check. It has been replaced by the elemental plans.