Two numbers on different bases
The client's budget is everything the project may spend: construction, design fees, other project costs, and VAT the client cannot recover. The cost plan is building works only, without VAT. Before you subtract one from the other, strip the budget down to construction without VAT.
- VAT £1,000,000
- Design fees £500,000
- Other project costs £200,000
- Construction budget £4,300,000