Presyuhan ang isang variation: ang pag-aayos ng PC at isang niche
Pagkatapos ng lektyur na ito, magagawa mong
Adjust a PC item by the actual price less the allowance, on the contract quantity.
Price new work at cost and add the same margin as the contract.
Get the variation in writing, signed, with GST added last.
1 / 3
In writing, signed, before the work
Under the Home Building Act 1989 (NSW), a variation to a residential building contract must be in writing and signed by both parties. Agree the price on paper before you build it. A verbal yes on site is not a variation you can rely on.
2 / 3
A PC item pays the difference
The allowance is already in the contract price. When the owners choose something dearer, the variation is the difference: actual price less allowance, on the quantity the contract priced. The first part of the new price is already paid for.
Halimbawa. Allowance $52.00 per m², chosen tile $74.00 per m², 14.20 m² in the contract. The variation is $22 × 14.2 = $312.40, not the full $1,050.80.
In the contract: allowance
$738
Owners' choice
$1,051 ($738 + $312)
3 / 3
New work at cost, then margin, then GST
Work that was not in the contract at all, such as a niche, is priced from cost: your hours, the subcontractor, the materials. All of it, new tiles included, at the new price. Then the contract's margin is added as a markup on cost, and GST last.
Price a tile upgrade and a shelf recess
Different numbers and a different margin from your task. Type your answer first.
Hindi ayon sa sukat
Ang problema
Tiles: allowance $52.00 per m² on 14.20 m² in the contract; the owners choose $74.00 per m².
Recess: 4 hours of yours at $58.00, tiler $55.00 per m² on 0.90 m² laid, 1.00 m² of new tiles to order, materials $66.00.
Margin 30% of the price, as a markup on cost. GST 10% last.
Difference per m²$22.00
Contract quantity14.20 m²
PC adjustment?
Difference per m²$22.00
Contract quantity14.20 m²
PC adjustment$312.40
Hakbang 1 ng 4
PC adjustment
New price less allowance, on the contract quantity. How much?
Pahiwatig: Only the difference per m² is new money.
($74.00 − $52.00) × 14.20 m² = $312.40.
$232$74$66
Your labour $232
Tiler $49.50
Tiles $74
Materials $66
$232$74$66
Your labour $232
Tiler $49.50
Tiles $74
Materials $66
Hakbang 2 ng 4
The recess at cost
Your hours, the tiler, the new tiles and the materials. What does it cost?
Pahiwatig: The recess is new work, so its tiles are at the full new price.
4 × $58.00 + 0.90 m² × $55.00 + 1.00 m² × $74.00 + $66.00 = $421.50.
1 PC adjustment
2 Recess
3 Margin
4 Price
1 PC adjustment
2 Recess
3 Margin
4 Price
Hakbang 3 ng 4
Variation price, without GST
Both parts, with the margin as a markup on cost. What is the price?
Pahiwatig: Add the two parts, then divide by 0.70.
$312.40 + $421.50 = $733.90. ÷ 0.70 = $1,048.43.
1 Without GST
2 GST
3 To sign
1 Without GST
2 GST
3 To sign
Hakbang 4 ng 4
To sign, with GST
Add GST once. What do the owners sign?
Pahiwatig: One tenth of the price, on top.
$1,048.43 × 1.10 = $1,153.27. The ERP variation takes $1,048.43; the signed paper shows $1,153.27.
Sa madaling salita. The PC item pays only the difference; new work is at cost; the margin goes on both; GST last; then both parties sign.
Subukin ang sarili
Tanong 1 ng 3
The PC allowance was priced on the tile order area, with waste. On which quantity do you adjust it?
Adjust on the quantity in the contract, so the two sides compare like with like.
The allowance was priced on the order area. Adjusting on less shortchanges you.
The tiler's labour is a separate line, not part of the PC item.
Tanong 2 ng 3
Allowance $45.00 per m², chosen tile $63.00 per m², 30 m² in the contract. What is the PC adjustment, before margin?
(63 − 45) × 30 = $540.00.
Tanong 3 ng 3
The owners agree to the niche on site and ask you to start. What do you do first?
A variation must be in writing and signed by both.
Then the price is open to argument after the work is done.
The final payment closes the original schedule. A variation is its own document.