OpenConstruction Academy
Prijava / Registracija
HR

Teorija prije zadatka 5 · 8 min

The PC item pays the difference

Vrednovanje izmjene: usklađenje PC-a i niša

Nakon ovog predavanja moći ćete

  1. Adjust a PC item by the actual price less the allowance, on the contract quantity.
  2. Price new work at cost and add the same margin as the contract.
  3. Get the variation in writing, signed, with GST added last.
1 / 3

In writing, signed, before the work

Under the Home Building Act 1989 (NSW), a variation to a residential building contract must be in writing and signed by both parties. Agree the price on paper before you build it. A verbal yes on site is not a variation you can rely on.

2 / 3

A PC item pays the difference

The allowance is already in the contract price. When the owners choose something dearer, the variation is the difference: actual price less allowance, on the quantity the contract priced. The first part of the new price is already paid for.

Primjer. Allowance $52.00 per m², chosen tile $74.00 per m², 14.20 m² in the contract. The variation is $22 × 14.2 = $312.40, not the full $1,050.80.
In the contract: allowance
$738
Owners' choice
$1,051 ($738 + $312)
3 / 3

New work at cost, then margin, then GST

Work that was not in the contract at all, such as a niche, is priced from cost: your hours, the subcontractor, the materials. All of it, new tiles included, at the new price. Then the contract's margin is added as a markup on cost, and GST last.

Price a tile upgrade and a shelf recess

Different numbers and a different margin from your task. Type your answer first.

Nije u mjerilu
Zadatak
  • Tiles: allowance $52.00 per m² on 14.20 m² in the contract; the owners choose $74.00 per m².
  • Recess: 4 hours of yours at $58.00, tiler $55.00 per m² on 0.90 m² laid, 1.00 m² of new tiles to order, materials $66.00.
  • Margin 30% of the price, as a markup on cost. GST 10% last.
Difference per m²$22.00
Contract quantity14.20 m²
PC adjustment?
Difference per m²$22.00
Contract quantity14.20 m²
PC adjustment$312.40
Korak 1 od 4

PC adjustment

New price less allowance, on the contract quantity. How much?

($74.00 − $52.00) × 14.20 m² = $312.40.

$232$74$66
  • Your labour $232
  • Tiler $49.50
  • Tiles $74
  • Materials $66
$232$74$66
  • Your labour $232
  • Tiler $49.50
  • Tiles $74
  • Materials $66
Korak 2 od 4

The recess at cost

Your hours, the tiler, the new tiles and the materials. What does it cost?

4 × $58.00 + 0.90 m² × $55.00 + 1.00 m² × $74.00 + $66.00 = $421.50.

+$3121+$4222?3?4
  • 1 PC adjustment
  • 2 Recess
  • 3 Margin
  • 4 Price
+$3121+$4222+$3153$1,0484
  • 1 PC adjustment
  • 2 Recess
  • 3 Margin
  • 4 Price
Korak 3 od 4

Variation price, without GST

Both parts, with the margin as a markup on cost. What is the price?

$312.40 + $421.50 = $733.90. ÷ 0.70 = $1,048.43.

$1,0481?2?3
  • 1 Without GST
  • 2 GST
  • 3 To sign
$1,0481+$1052$1,1533
  • 1 Without GST
  • 2 GST
  • 3 To sign
Korak 4 od 4

To sign, with GST

Add GST once. What do the owners sign?

$1,048.43 × 1.10 = $1,153.27. The ERP variation takes $1,048.43; the signed paper shows $1,153.27.

Ukratko. The PC item pays only the difference; new work is at cost; the margin goes on both; GST last; then both parties sign.

Provjerite se

Pitanje 1 od 3

The PC allowance was priced on the tile order area, with waste. On which quantity do you adjust it?

  • Adjust on the quantity in the contract, so the two sides compare like with like.

  • The allowance was priced on the order area. Adjusting on less shortchanges you.

  • The tiler's labour is a separate line, not part of the PC item.

Pitanje 2 od 3

Allowance $45.00 per m², chosen tile $63.00 per m², 30 m² in the contract. What is the PC adjustment, before margin?

(63 − 45) × 30 = $540.00.
Pitanje 3 od 3

The owners agree to the niche on site and ask you to start. What do you do first?

  • A variation must be in writing and signed by both.

  • Then the price is open to argument after the work is done.

  • The final payment closes the original schedule. A variation is its own document.