OpenConstruction Academy
Mag-sign in / Magrehistro
FIL

Teorya bago ang gawain 1 · 10 min

Durations from quantities, crews and a working calendar

Mga duration at logic ng natitirang trabaho

Panimula ng kurso

Pagkatapos ng lektyur na ito, magagawa mong

  1. Turn a quantity and a crew output into a duration in whole working days.
  2. Convert a subcontractor's quote in weeks into working days on a five-day calendar.
  3. Link activities finish-to-start and read when a successor can begin.
1 / 3

Duration is quantity over output

A duration in a schedule is not a guess. Take the quantity of the activity from the takeoff and divide it by what the crew installs in a working day. The result is rarely a whole number. Round it up: a crew that needs part of a day still occupies that day on site, and nobody else can use it.

Halimbawa. 3,700 sq ft at 520 sq ft a day is 7.12 days. The schedule shows 8: the eighth day is short, but it is still a day of that crew on that floor.
Ceiling grid, sq ft3,700
One crew installs per day, sq ft520
Quantity ÷ output7.12
Duration, working days8
2 / 3

Crews add output, not quantity

When two crews work the same area, the quantity stays the same and the daily output doubles. Divide by the combined output of every crew on the activity. The common slip is to take one crew's output and forget the others, which plans the work at twice its real length.

Halimbawa. 8,800 sq ft of board, each crew hangs 1,000 sq ft a day. One crew: 8.8 days, so 9. Two crews: 4.4 days, so 5. The quantity never changed.
One crew
9
Two crews
5
Three crews
3
3 / 3

Weeks, working days and normal weather

Most US schedules run on a Monday-to-Friday calendar, so a week of work is five working days. A subcontractor who quotes in weeks means weeks of work: multiply by five, then add the odd days. Outdoor work also needs the rain and frost days the site can expect in that season. Those normal weather days go into the outdoor durations from the start; only weather worse than normal can later support a time extension.

Halimbawa. A roofer quotes 8 weeks: 40 working days, not 8 weeks of seven days. Sitework that needs 36 dry days in weeks whose weather normals show 4 adverse days is planned at 40 days.

Durations for a medical office fit-out

Another job: the interior of a two-storey medical office. Work out three durations, then link two of them.

Hindi ayon sa sukat
Ang problema
  • Metal stud framing: 5,500 lf, 2 crews, each 340 lf a day.
  • Tape and finish: 14,800 sq ft, 3 finishers, each 650 sq ft a day.
  • The roofing subcontractor quotes 2 weeks and 1 working day.
  • Calendar Monday to Friday. Framing starts on the data date, day 0.
Framing, lf5,500
Output of 2 crews per day, lf680
Duration, working days?
Framing, lf5,500
Output of 2 crews per day, lf680
Duration, working days9
Hakbang 1 ng 4

Framing

What is the framing duration in working days?

5,500 ÷ (2 × 340) = 8.09 days. Round up: 9 working days.

Hakbang 2 ng 4

Tape and finish

What is the tape and finish duration?

14,800 ÷ (3 × 650) = 7.59 days. Round up: 8 working days.

Hakbang 3 ng 4

Roofing quote

How many working days do you enter for the roofing?

2 × 5 + 1 = 11 working days. Counted as seven-day weeks it would plan the roofers on Saturdays and Sundays.

Framing, then tape and finish
17 (9 + 8)
Roofing, from day 0
11
Framing, then tape and finish
17 (9 + 8)
Roofing, from day 0
11
Hakbang 4 ng 4

Logic

Tape and finish follows framing, finish-to-start, no lag. At which working day does tape and finish end, counting from day 0?

Framing runs from day 0 to day 9. Tape and finish starts there and ends at day 17. In calendar terms it starts on the next working day after framing ends.

Sa madaling salita. Quantity over the output of every crew on it, rounded up. Weeks are five working days. Logic sets when each activity can start.

Subukin ang sarili

Tanong 1 ng 3

Floor tile: 4,100 sq ft. Three tile setters each lay 200 sq ft a day. What duration do you enter, in working days?

4,100 ÷ (3 × 200) = 6.83 days. Round up: 7 working days.
Tanong 2 ng 3

Your schedule runs Monday to Friday. A subcontractor quotes "three weeks". What do you enter?

  • Right. A week of work on this calendar is five working days.

  • That counts seven-day weeks and plans the crew on weekends.

  • Lag is waiting time between activities, not working time inside one.

Tanong 3 ng 3

Paving needs eight dry days. The weather normals for those weeks show two adverse days. What is the planned duration?

  • Only weather worse than normal can support a claim. Normal weather is yours to plan for.

  • Right. The expected weather is part of the outdoor duration from the start.

  • A floating weather activity hides the days where they will fall. Put them in the outdoor work itself.