Panimula ng kurso · 3 min
CPM schedule at mga extension ng oras (US, AIA A201)
You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.
Kathang-isip na proyekto- Building
- Three storeys: retail on a concrete podium, two floors of wood-frame apartments
- Contract
- AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
- Story
- Schedule update, February to May 2027
- Trabaho sa ERP
- 5 gawain, mga 2 oras 45 min
Sino ang nagbibigay ng ano kanino
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dumarating sa iyo
- Elevator subcontractorQuotes the installation
- Quote in weeksGawain 1
- The ownerOwner, signs change orders
- CO-05Gawain 3
- CO-03Gawain 4
- SuperintendentYour firm, keeps the daily reports
- Daily reportsGawain 5
Lumalabas sa iyo
- Schedule updateGawain 1
- Critical pathGawain 2
- CO-05 time analysisGawain 3
- CO-03 fragnetGawain 4
- Weather claimGawain 5
Ang ruta mo sa proyekto
Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.
The update
Gawain 1 · 30 min
Mga duration at logic ng natitirang trabaho
- Ang gagawin mo
- The remaining work as a network
- Dokumento
- Quantities, crew outputs, the elevator quote
- Sa ERP
- Schedule
The update
Gawain 2 · 30 min
Critical path, float at ang planadong pagtatapos
- Ang gagawin mo
- Critical path, planned length, and the elevator's float (spare time)
- Dokumento
- The update for the project manager
- Sa ERP
- Schedule, Critical Path
Owner changes
Gawain 3 · 30 min
Pagbabago ng may-ari na wala sa critical path
- Ang gagawin mo
- Float used by CO-05, and the extension if any
- Dokumento
- Change Order CO-05, storefront glass
- Sa ERP
- Schedule
Owner changes
Gawain 4 · 35 min
Pagbabago ng may-ari sa critical path: ang fragnet
- Ang gagawin mo
- The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
- Dokumento
- Change Order CO-03, quartz countertops
- Sa ERP
- Schedule
Weather
Gawain 5 · 40 min
Abnormal na panahon at sabayang delay
- Ang gagawin mo
- The weather extension, apart from your own delay
- Dokumento
- Daily reports and weather normals
- Sa ERP
- Schedule
How an event becomes days on the contract
Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.
Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.
Sa madaling salita. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.