Panimula ng kurso · 3 min

CPM schedule at mga extension ng oras (US, AIA A201)

You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.

Simulan ang gawain 1

The site: a three-storey mixed-use building with a concrete retail podium and wood-frame apartment floors above.Kathang-isip na proyekto
Quillfield CommonsMixed-use building, retail and apartments
Building
Three storeys: retail on a concrete podium, two floors of wood-frame apartments
Contract
AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
Story
Schedule update, February to May 2027
Trabaho sa ERP
5 gawain, mga 2 oras 45 min

Sino ang nagbibigay ng ano kanino

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dumarating sa iyo

  • Elevator subcontractorQuotes the installation
    • Quote in weeksGawain 1
  • The ownerOwner, signs change orders
    • CO-05Gawain 3
    • CO-03Gawain 4
  • SuperintendentYour firm, keeps the daily reports
    • Daily reportsGawain 5
IkawProject scheduler, general contractor

Lumalabas sa iyo

    • Schedule updateGawain 1
    • Critical pathGawain 2
    Project managerYour firm, signs the update
    • CO-05 time analysisGawain 3
    • CO-03 fragnetGawain 4
    • Weather claimGawain 5
    ArchitectDecides extensions under A201

Ang ruta mo sa proyekto

Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.

  1. The update

    Gawain 1 · 30 min

    Mga duration at logic ng natitirang trabaho

    Ang gagawin mo
    The remaining work as a network
    Dokumento
    Quantities, crew outputs, the elevator quote
    Sa ERP
    Schedule
  2. The update

    Gawain 2 · 30 min

    Critical path, float at ang planadong pagtatapos

    Ang gagawin mo
    Critical path, planned length, and the elevator's float (spare time)
    Dokumento
    The update for the project manager
    Sa ERP
    Schedule, Critical Path
  3. Owner changes

    Gawain 3 · 30 min

    Pagbabago ng may-ari na wala sa critical path

    Ang gagawin mo
    Float used by CO-05, and the extension if any
    Dokumento
    Change Order CO-05, storefront glass
    Sa ERP
    Schedule
  4. Owner changes

    Gawain 4 · 35 min

    Pagbabago ng may-ari sa critical path: ang fragnet

    Ang gagawin mo
    The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
    Dokumento
    Change Order CO-03, quartz countertops
    Sa ERP
    Schedule
  5. Weather

    Gawain 5 · 40 min

    Abnormal na panahon at sabayang delay

    Ang gagawin mo
    The weather extension, apart from your own delay
    Dokumento
    Daily reports and weather normals
    Sa ERP
    Schedule

How an event becomes days on the contract

Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.

Critical path
Gawain 2Planned lengthThe longest path sets the finish. Shorter paths carry float.
Same finish
Gawain 3CO-05The change spends float. The finish does not move.
CO-03Planned length
Gawain 4CO-03A fragnet, the change drawn as a small network, on the critical path moves the finish day for day.
WeatherCO-03Planned length
Gawain 5WeatherAbnormal days, less the float left, earn time. Your own delay earns none.

Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.

Sa madaling salita. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.