Kursuse sissejuhatus · 3 min
CPM-ajakava ja tähtaja pikendamine (USA, AIA A201)
You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.
Väljamõeldud projekt- Building
- Three storeys: retail on a concrete podium, two floors of wood-frame apartments
- Contract
- AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
- Story
- Schedule update, February to May 2027
- Töö ERP-s
- Ülesandeid 5, umbes 2 h 45 min
Kes annab kellele mida
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tuleb sinule
- Elevator subcontractorQuotes the installation
- Quote in weeksÜlesanne 1
- The ownerOwner, signs change orders
- CO-05Ülesanne 3
- CO-03Ülesanne 4
- SuperintendentYour firm, keeps the daily reports
- Daily reportsÜlesanne 5
Läheb sinult
- Schedule updateÜlesanne 1
- Critical pathÜlesanne 2
- CO-05 time analysisÜlesanne 3
- CO-03 fragnetÜlesanne 4
- Weather claimÜlesanne 5
Sinu tee läbi projekti
Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.
The update
Ülesanne 1 · 30 min
Allesjäänud töö kestused ja loogika
- Sinu tulemus
- The remaining work as a network
- Dokument
- Quantities, crew outputs, the elevator quote
- ERP-s
- Schedule
The update
Ülesanne 2 · 30 min
Kriitiline tee, reserv ja planeeritud lõpp
- Sinu tulemus
- Critical path, planned length, and the elevator's float (spare time)
- Dokument
- The update for the project manager
- ERP-s
- Schedule, Critical Path
Owner changes
Ülesanne 3 · 30 min
Omaniku muudatus väljaspool kriitilist teed
- Sinu tulemus
- Float used by CO-05, and the extension if any
- Dokument
- Change Order CO-05, storefront glass
- ERP-s
- Schedule
Owner changes
Ülesanne 4 · 35 min
Omaniku muudatus kriitilisel teel: fragnet
- Sinu tulemus
- The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
- Dokument
- Change Order CO-03, quartz countertops
- ERP-s
- Schedule
Weather
Ülesanne 5 · 40 min
Ebanormaalne ilm ja samaaegne viivitus
- Sinu tulemus
- The weather extension, apart from your own delay
- Dokument
- Daily reports and weather normals
- ERP-s
- Schedule
How an event becomes days on the contract
Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.