CPM график и удължаване на срока (САЩ, AIA A201)

You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.

Започнете задача 1

The site: a three-storey mixed-use building with a concrete retail podium and wood-frame apartment floors above.Измислен проект
Quillfield CommonsMixed-use building, retail and apartments
Building
Three storeys: retail on a concrete podium, two floors of wood-frame apartments
Contract
AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
Story
Schedule update, February to May 2027
Работа в ERP
Задачи: 5, около 2 ч 45 мин

Кой какво предава на кого

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Идва при вас

  • Elevator subcontractorQuotes the installation
    • Quote in weeksЗадача 1
  • The ownerOwner, signs change orders
    • CO-05Задача 3
    • CO-03Задача 4
  • SuperintendentYour firm, keeps the daily reports
    • Daily reportsЗадача 5
ВиеProject scheduler, general contractor

Тръгва от вас

    • Schedule updateЗадача 1
    • Critical pathЗадача 2
    Project managerYour firm, signs the update
    • CO-05 time analysisЗадача 3
    • CO-03 fragnetЗадача 4
    • Weather claimЗадача 5
    ArchitectDecides extensions under A201

Вашият път през проекта

Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.

  1. The update

    Задача 1 · 30 мин

    Продължителности и логика на оставащите работи

    Вашият резултат
    The remaining work as a network
    Документ
    Quantities, crew outputs, the elevator quote
    В ERP
    Schedule
  2. The update

    Задача 2 · 30 мин

    Критичен път, резерв и планирано завършване

    Вашият резултат
    Critical path, planned length, and the elevator's float (spare time)
    Документ
    The update for the project manager
    В ERP
    Schedule, Critical Path
  3. Owner changes

    Задача 3 · 30 мин

    Промяна от собственика извън критичния път

    Вашият резултат
    Float used by CO-05, and the extension if any
    Документ
    Change Order CO-05, storefront glass
    В ERP
    Schedule
  4. Owner changes

    Задача 4 · 35 мин

    Промяна от собственика върху критичния път: fragnet

    Вашият резултат
    The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
    Документ
    Change Order CO-03, quartz countertops
    В ERP
    Schedule
  5. Weather

    Задача 5 · 40 мин

    Необичайно време и едновременно забавяне

    Вашият резултат
    The weather extension, apart from your own delay
    Документ
    Daily reports and weather normals
    В ERP
    Schedule

How an event becomes days on the contract

Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.

Critical path
Задача 2Planned lengthThe longest path sets the finish. Shorter paths carry float.
Same finish
Задача 3CO-05The change spends float. The finish does not move.
CO-03Planned length
Задача 4CO-03A fragnet, the change drawn as a small network, on the critical path moves the finish day for day.
WeatherCO-03Planned length
Задача 5WeatherAbnormal days, less the float left, earn time. Your own delay earns none.

В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.

Накратко. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.