CPM график и удължаване на срока (САЩ, AIA A201)
You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.
Измислен проект- Building
- Three storeys: retail on a concrete podium, two floors of wood-frame apartments
- Contract
- AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
- Story
- Schedule update, February to May 2027
- Работа в ERP
- Задачи: 5, около 2 ч 45 мин
Кой какво предава на кого
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Идва при вас
- Elevator subcontractorQuotes the installation
- Quote in weeksЗадача 1
- The ownerOwner, signs change orders
- CO-05Задача 3
- CO-03Задача 4
- SuperintendentYour firm, keeps the daily reports
- Daily reportsЗадача 5
Тръгва от вас
- Schedule updateЗадача 1
- Critical pathЗадача 2
- CO-05 time analysisЗадача 3
- CO-03 fragnetЗадача 4
- Weather claimЗадача 5
Вашият път през проекта
Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.
The update
Задача 1 · 30 мин
Продължителности и логика на оставащите работи
- Вашият резултат
- The remaining work as a network
- Документ
- Quantities, crew outputs, the elevator quote
- В ERP
- Schedule
The update
Задача 2 · 30 мин
Критичен път, резерв и планирано завършване
- Вашият резултат
- Critical path, planned length, and the elevator's float (spare time)
- Документ
- The update for the project manager
- В ERP
- Schedule, Critical Path
Owner changes
Задача 3 · 30 мин
Промяна от собственика извън критичния път
- Вашият резултат
- Float used by CO-05, and the extension if any
- Документ
- Change Order CO-05, storefront glass
- В ERP
- Schedule
Owner changes
Задача 4 · 35 мин
Промяна от собственика върху критичния път: fragnet
- Вашият резултат
- The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
- Документ
- Change Order CO-03, quartz countertops
- В ERP
- Schedule
Weather
Задача 5 · 40 мин
Необичайно време и едновременно забавяне
- Вашият резултат
- The weather extension, apart from your own delay
- Документ
- Daily reports and weather normals
- В ERP
- Schedule
How an event becomes days on the contract
Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.
В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.
Накратко. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.