زمان‌بندی CPM و تمدید مدت (آمریکا، AIA A201)

You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.

شروع تکلیف 1

The site: a three-storey mixed-use building with a concrete retail podium and wood-frame apartment floors above.پروژهٔ خیالی
Quillfield CommonsMixed-use building, retail and apartments
Building
Three storeys: retail on a concrete podium, two floors of wood-frame apartments
Contract
AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
Story
Schedule update, February to May 2027
کار در ERP
5 تکلیف، حدود 2 ساعت 45 دقیقه

چه کسی چه چیزی به چه کسی می‌دهد

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

به شما می‌رسد

  • Elevator subcontractorQuotes the installation
    • Quote in weeksتکلیف 1
  • The ownerOwner, signs change orders
    • CO-05تکلیف 3
    • CO-03تکلیف 4
  • SuperintendentYour firm, keeps the daily reports
    • Daily reportsتکلیف 5
شماProject scheduler, general contractor

از شما می‌رود

    • Schedule updateتکلیف 1
    • Critical pathتکلیف 2
    Project managerYour firm, signs the update
    • CO-05 time analysisتکلیف 3
    • CO-03 fragnetتکلیف 4
    • Weather claimتکلیف 5
    ArchitectDecides extensions under A201

مسیر شما در پروژه

Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.

  1. The update

    تکلیف 1 · 30 دقیقه

    مدت و منطق کارهای باقی‌مانده

    خروجی شما
    The remaining work as a network
    سند
    Quantities, crew outputs, the elevator quote
    در ERP
    Schedule
  2. The update

    تکلیف 2 · 30 دقیقه

    مسیر بحرانی، شناوری و پایان برنامه‌ریزی‌شده

    خروجی شما
    Critical path, planned length, and the elevator's float (spare time)
    سند
    The update for the project manager
    در ERP
    Schedule, Critical Path
  3. Owner changes

    تکلیف 3 · 30 دقیقه

    تغییر کارفرما خارج از مسیر بحرانی

    خروجی شما
    Float used by CO-05, and the extension if any
    سند
    Change Order CO-05, storefront glass
    در ERP
    Schedule
  4. Owner changes

    تکلیف 4 · 35 دقیقه

    تغییر کارفرما روی مسیر بحرانی: فرگ‌نت

    خروجی شما
    The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
    سند
    Change Order CO-03, quartz countertops
    در ERP
    Schedule
  5. Weather

    تکلیف 5 · 40 دقیقه

    آب‌وهوای غیرعادی و تأخیر همزمان

    خروجی شما
    The weather extension, apart from your own delay
    سند
    Daily reports and weather normals
    در ERP
    Schedule

How an event becomes days on the contract

Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.

Critical path
تکلیف 2Planned lengthThe longest path sets the finish. Shorter paths carry float.
Same finish
تکلیف 3CO-05The change spends float. The finish does not move.
CO-03Planned length
تکلیف 4CO-03A fragnet, the change drawn as a small network, on the critical path moves the finish day for day.
WeatherCO-03Planned length
تکلیف 5WeatherAbnormal days, less the float left, earn time. Your own delay earns none.

آبی چیزی است که تکلیف اضافه می‌کند؛ خاکستری از مرحلهٔ قبل آمده است.

به‌طور خلاصه. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.