Introduktion till kursen · 3 min
CPM-tidsplan och tidsförlängning (USA, AIA A201)
You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.
Fiktivt projekt- Building
- Three storeys: retail on a concrete podium, two floors of wood-frame apartments
- Contract
- AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
- Story
- Schedule update, February to May 2027
- Arbete i ERP
- 5 uppgifter, cirka 2 h 45 min
Vem lämnar vad till vem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer till dig
- Elevator subcontractorQuotes the installation
- Quote in weeksUppgift 1
- The ownerOwner, signs change orders
- CO-05Uppgift 3
- CO-03Uppgift 4
- SuperintendentYour firm, keeps the daily reports
- Daily reportsUppgift 5
Går från dig
- Schedule updateUppgift 1
- Critical pathUppgift 2
- CO-05 time analysisUppgift 3
- CO-03 fragnetUppgift 4
- Weather claimUppgift 5
Din väg genom projektet
Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.
The update
Uppgift 1 · 30 min
Varaktigheter och logik för kvarvarande arbeten
- Du tar fram
- The remaining work as a network
- Dokument
- Quantities, crew outputs, the elevator quote
- I ERP
- Schedule
The update
Uppgift 2 · 30 min
Kritisk väg, marginal och planerat slutdatum
- Du tar fram
- Critical path, planned length, and the elevator's float (spare time)
- Dokument
- The update for the project manager
- I ERP
- Schedule, Critical Path
Owner changes
Uppgift 3 · 30 min
En ägarändring utanför den kritiska vägen
- Du tar fram
- Float used by CO-05, and the extension if any
- Dokument
- Change Order CO-05, storefront glass
- I ERP
- Schedule
Owner changes
Uppgift 4 · 35 min
En ägarändring på den kritiska vägen: fragnet
- Du tar fram
- The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
- Dokument
- Change Order CO-03, quartz countertops
- I ERP
- Schedule
Weather
Uppgift 5 · 40 min
Onormalt väder och samtidig försening
- Du tar fram
- The weather extension, apart from your own delay
- Dokument
- Daily reports and weather normals
- I ERP
- Schedule
How an event becomes days on the contract
Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.
Blått är det uppgiften lägger till; grått följer med från tidigare.
Kort sagt. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.