Introduktion till kursen · 3 min

CPM-tidsplan och tidsförlängning (USA, AIA A201)

You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.

Starta uppgift 1

The site: a three-storey mixed-use building with a concrete retail podium and wood-frame apartment floors above.Fiktivt projekt
Quillfield CommonsMixed-use building, retail and apartments
Building
Three storeys: retail on a concrete podium, two floors of wood-frame apartments
Contract
AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
Story
Schedule update, February to May 2027
Arbete i ERP
5 uppgifter, cirka 2 h 45 min

Vem lämnar vad till vem

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Kommer till dig

  • Elevator subcontractorQuotes the installation
    • Quote in weeksUppgift 1
  • The ownerOwner, signs change orders
    • CO-05Uppgift 3
    • CO-03Uppgift 4
  • SuperintendentYour firm, keeps the daily reports
    • Daily reportsUppgift 5
DuProject scheduler, general contractor

Går från dig

    • Schedule updateUppgift 1
    • Critical pathUppgift 2
    Project managerYour firm, signs the update
    • CO-05 time analysisUppgift 3
    • CO-03 fragnetUppgift 4
    • Weather claimUppgift 5
    ArchitectDecides extensions under A201

Din väg genom projektet

Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.

  1. The update

    Uppgift 1 · 30 min

    Varaktigheter och logik för kvarvarande arbeten

    Du tar fram
    The remaining work as a network
    Dokument
    Quantities, crew outputs, the elevator quote
    I ERP
    Schedule
  2. The update

    Uppgift 2 · 30 min

    Kritisk väg, marginal och planerat slutdatum

    Du tar fram
    Critical path, planned length, and the elevator's float (spare time)
    Dokument
    The update for the project manager
    I ERP
    Schedule, Critical Path
  3. Owner changes

    Uppgift 3 · 30 min

    En ägarändring utanför den kritiska vägen

    Du tar fram
    Float used by CO-05, and the extension if any
    Dokument
    Change Order CO-05, storefront glass
    I ERP
    Schedule
  4. Owner changes

    Uppgift 4 · 35 min

    En ägarändring på den kritiska vägen: fragnet

    Du tar fram
    The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
    Dokument
    Change Order CO-03, quartz countertops
    I ERP
    Schedule
  5. Weather

    Uppgift 5 · 40 min

    Onormalt väder och samtidig försening

    Du tar fram
    The weather extension, apart from your own delay
    Dokument
    Daily reports and weather normals
    I ERP
    Schedule

How an event becomes days on the contract

Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.

Critical path
Uppgift 2Planned lengthThe longest path sets the finish. Shorter paths carry float.
Same finish
Uppgift 3CO-05The change spends float. The finish does not move.
CO-03Planned length
Uppgift 4CO-03A fragnet, the change drawn as a small network, on the critical path moves the finish day for day.
WeatherCO-03Planned length
Uppgift 5WeatherAbnormal days, less the float left, earn time. Your own delay earns none.

Blått är det uppgiften lägger till; grått följer med från tidigare.

Kort sagt. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.