CPM-tidsplan og fristforlængelser (USA, AIA A201)
You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.
Fiktivt projekt- Building
- Three storeys: retail on a concrete podium, two floors of wood-frame apartments
- Contract
- AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
- Story
- Schedule update, February to May 2027
- Arbejde i ERP
- 5 opgaver, cirka 2 t 45 min
Hvem giver hvad til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til dig
- Elevator subcontractorQuotes the installation
- Quote in weeksOpgave 1
- The ownerOwner, signs change orders
- CO-05Opgave 3
- CO-03Opgave 4
- SuperintendentYour firm, keeps the daily reports
- Daily reportsOpgave 5
Går fra dig
- Schedule updateOpgave 1
- Critical pathOpgave 2
- CO-05 time analysisOpgave 3
- CO-03 fragnetOpgave 4
- Weather claimOpgave 5
Din vej gennem sagen
Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.
The update
Opgave 1 · 30 min
Varigheder og logik i det resterende arbejde
- Du leverer
- The remaining work as a network
- Dokument
- Quantities, crew outputs, the elevator quote
- I ERP
- Schedule
The update
Opgave 2 · 30 min
Kritisk vej, tidsreserve og planlagt afslutning
- Du leverer
- Critical path, planned length, and the elevator's float (spare time)
- Dokument
- The update for the project manager
- I ERP
- Schedule, Critical Path
Owner changes
Opgave 3 · 30 min
En bygherreændring uden for den kritiske vej
- Du leverer
- Float used by CO-05, and the extension if any
- Dokument
- Change Order CO-05, storefront glass
- I ERP
- Schedule
Owner changes
Opgave 4 · 35 min
En bygherreændring på den kritiske vej: fragnettet
- Du leverer
- The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
- Dokument
- Change Order CO-03, quartz countertops
- I ERP
- Schedule
Weather
Opgave 5 · 40 min
Usædvanligt vejr og en sammenfaldende forsinkelse
- Du leverer
- The weather extension, apart from your own delay
- Dokument
- Daily reports and weather normals
- I ERP
- Schedule
How an event becomes days on the contract
Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.
Blå er det, opgaven tilføjer; grå er overført fra før.
Kort sagt. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.