Grafic CPM și prelungiri de termen (SUA, AIA A201)

You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.

Începe sarcina 1

The site: a three-storey mixed-use building with a concrete retail podium and wood-frame apartment floors above.Proiect fictiv
Quillfield CommonsMixed-use building, retail and apartments
Building
Three storeys: retail on a concrete podium, two floors of wood-frame apartments
Contract
AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
Story
Schedule update, February to May 2027
Lucru în ERP
5 sarcini, circa 2 h 45 min

Cine ce predă cui

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Ajunge la tine

  • Elevator subcontractorQuotes the installation
    • Quote in weeksSarcina 1
  • The ownerOwner, signs change orders
    • CO-05Sarcina 3
    • CO-03Sarcina 4
  • SuperintendentYour firm, keeps the daily reports
    • Daily reportsSarcina 5
TuProject scheduler, general contractor

Pleacă de la tine

    • Schedule updateSarcina 1
    • Critical pathSarcina 2
    Project managerYour firm, signs the update
    • CO-05 time analysisSarcina 3
    • CO-03 fragnetSarcina 4
    • Weather claimSarcina 5
    ArchitectDecides extensions under A201

Traseul tău prin proiect

Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.

  1. The update

    Sarcina 1 · 30 min

    Durate și logica lucrărilor rămase

    Produci
    The remaining work as a network
    Document
    Quantities, crew outputs, the elevator quote
    În ERP
    Schedule
  2. The update

    Sarcina 2 · 30 min

    Drumul critic, rezerva și finalizarea planificată

    Produci
    Critical path, planned length, and the elevator's float (spare time)
    Document
    The update for the project manager
    În ERP
    Schedule, Critical Path
  3. Owner changes

    Sarcina 3 · 30 min

    O modificare a beneficiarului în afara drumului critic

    Produci
    Float used by CO-05, and the extension if any
    Document
    Change Order CO-05, storefront glass
    În ERP
    Schedule
  4. Owner changes

    Sarcina 4 · 35 min

    O modificare a beneficiarului pe drumul critic: fragnetul

    Produci
    The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
    Document
    Change Order CO-03, quartz countertops
    În ERP
    Schedule
  5. Weather

    Sarcina 5 · 40 min

    Vreme anormală și întârziere concurentă

    Produci
    The weather extension, apart from your own delay
    Document
    Daily reports and weather normals
    În ERP
    Schedule

How an event becomes days on the contract

Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.

Critical path
Sarcina 2Planned lengthThe longest path sets the finish. Shorter paths carry float.
Same finish
Sarcina 3CO-05The change spends float. The finish does not move.
CO-03Planned length
Sarcina 4CO-03A fragnet, the change drawn as a small network, on the critical path moves the finish day for day.
WeatherCO-03Planned length
Sarcina 5WeatherAbnormal days, less the float left, earn time. Your own delay earns none.

Albastru este ce adaugă sarcina; gri este ce vine de dinainte.

Pe scurt. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.