CPM raspored i produljenje rokova (SAD, AIA A201)

You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.

Započni zadatak 1

The site: a three-storey mixed-use building with a concrete retail podium and wood-frame apartment floors above.Izmišljeni projekt
Quillfield CommonsMixed-use building, retail and apartments
Building
Three storeys: retail on a concrete podium, two floors of wood-frame apartments
Contract
AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
Story
Schedule update, February to May 2027
Rad u ERP-u
Zadataka: 5, oko 2 h 45 min

Tko kome što predaje

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dolazi vama

  • Elevator subcontractorQuotes the installation
    • Quote in weeksZadatak 1
  • The ownerOwner, signs change orders
    • CO-05Zadatak 3
    • CO-03Zadatak 4
  • SuperintendentYour firm, keeps the daily reports
    • Daily reportsZadatak 5
ViProject scheduler, general contractor

Odlazi od vas

    • Schedule updateZadatak 1
    • Critical pathZadatak 2
    Project managerYour firm, signs the update
    • CO-05 time analysisZadatak 3
    • CO-03 fragnetZadatak 4
    • Weather claimZadatak 5
    ArchitectDecides extensions under A201

Vaš put kroz projekt

Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.

  1. The update

    Zadatak 1 · 30 min

    Trajanja i logika preostalih radova

    Vaš rezultat
    The remaining work as a network
    Dokument
    Quantities, crew outputs, the elevator quote
    U ERP-u
    Schedule
  2. The update

    Zadatak 2 · 30 min

    Kritični put, rezerva i planirani završetak

    Vaš rezultat
    Critical path, planned length, and the elevator's float (spare time)
    Dokument
    The update for the project manager
    U ERP-u
    Schedule, Critical Path
  3. Owner changes

    Zadatak 3 · 30 min

    Izmjena naručitelja izvan kritičnog puta

    Vaš rezultat
    Float used by CO-05, and the extension if any
    Dokument
    Change Order CO-05, storefront glass
    U ERP-u
    Schedule
  4. Owner changes

    Zadatak 4 · 35 min

    Izmjena naručitelja na kritičnom putu: fragnet

    Vaš rezultat
    The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
    Dokument
    Change Order CO-03, quartz countertops
    U ERP-u
    Schedule
  5. Weather

    Zadatak 5 · 40 min

    Neuobičajeno vrijeme i istodobno kašnjenje

    Vaš rezultat
    The weather extension, apart from your own delay
    Dokument
    Daily reports and weather normals
    U ERP-u
    Schedule

How an event becomes days on the contract

Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.

Critical path
Zadatak 2Planned lengthThe longest path sets the finish. Shorter paths carry float.
Same finish
Zadatak 3CO-05The change spends float. The finish does not move.
CO-03Planned length
Zadatak 4CO-03A fragnet, the change drawn as a small network, on the critical path moves the finish day for day.
WeatherCO-03Planned length
Zadatak 5WeatherAbnormal days, less the float left, earn time. Your own delay earns none.

Plavo je ono što zadatak dodaje; sivo se prenosi od prije.

Ukratko. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.