Сургалтын танилцуулга · 3 мин
CPM график ба хугацаа сунгалт (АНУ, AIA A201)
You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.
Зохиомол төсөл- Building
- Three storeys: retail on a concrete podium, two floors of wood-frame apartments
- Contract
- AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
- Story
- Schedule update, February to May 2027
- ERP дээрх ажил
- Даалгавар: 5, ойролцоогоор 2 цаг 45 мин
Хэн хэнд юу дамжуулдаг
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Танд ирдэг
- Elevator subcontractorQuotes the installation
- Quote in weeksДаалгавар 1
- The ownerOwner, signs change orders
- CO-05Даалгавар 3
- CO-03Даалгавар 4
- SuperintendentYour firm, keeps the daily reports
- Daily reportsДаалгавар 5
Танаас гардаг
- Schedule updateДаалгавар 1
- Critical pathДаалгавар 2
- CO-05 time analysisДаалгавар 3
- CO-03 fragnetДаалгавар 4
- Weather claimДаалгавар 5
Төслөөр явах таны зам
Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.
The update
Даалгавар 1 · 30 мин
Үлдсэн ажлын үргэлжлэх хугацаа ба логик
- Үр дүн
- The remaining work as a network
- Баримт бичиг
- Quantities, crew outputs, the elevator quote
- ERP дээр
- Schedule
The update
Даалгавар 2 · 30 мин
Критик зам, нөөц хугацаа ба төлөвлөсөн дуусгалт
- Үр дүн
- Critical path, planned length, and the elevator's float (spare time)
- Баримт бичиг
- The update for the project manager
- ERP дээр
- Schedule, Critical Path
Owner changes
Даалгавар 3 · 30 мин
Критик замаас гадуурх захиалагчийн өөрчлөлт
- Үр дүн
- Float used by CO-05, and the extension if any
- Баримт бичиг
- Change Order CO-05, storefront glass
- ERP дээр
- Schedule
Owner changes
Даалгавар 4 · 35 мин
Критик замын захиалагчийн өөрчлөлт: фрагнет
- Үр дүн
- The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
- Баримт бичиг
- Change Order CO-03, quartz countertops
- ERP дээр
- Schedule
Weather
Даалгавар 5 · 40 мин
Ердийн бус цаг агаар ба зэрэгцээ хоцролт
- Үр дүн
- The weather extension, apart from your own delay
- Баримт бичиг
- Daily reports and weather normals
- ERP дээр
- Schedule
How an event becomes days on the contract
Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.
Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.
Товчхондоо. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.