Сургалтын танилцуулга · 3 мин

CPM график ба хугацаа сунгалт (АНУ, AIA A201)

You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.

1-р даалгаврыг эхлэх

The site: a three-storey mixed-use building with a concrete retail podium and wood-frame apartment floors above.Зохиомол төсөл
Quillfield CommonsMixed-use building, retail and apartments
Building
Three storeys: retail on a concrete podium, two floors of wood-frame apartments
Contract
AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
Story
Schedule update, February to May 2027
ERP дээрх ажил
Даалгавар: 5, ойролцоогоор 2 цаг 45 мин

Хэн хэнд юу дамжуулдаг

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Танд ирдэг

  • Elevator subcontractorQuotes the installation
    • Quote in weeksДаалгавар 1
  • The ownerOwner, signs change orders
    • CO-05Даалгавар 3
    • CO-03Даалгавар 4
  • SuperintendentYour firm, keeps the daily reports
    • Daily reportsДаалгавар 5
ТаProject scheduler, general contractor

Танаас гардаг

    • Schedule updateДаалгавар 1
    • Critical pathДаалгавар 2
    Project managerYour firm, signs the update
    • CO-05 time analysisДаалгавар 3
    • CO-03 fragnetДаалгавар 4
    • Weather claimДаалгавар 5
    ArchitectDecides extensions under A201

Төслөөр явах таны зам

Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.

  1. The update

    Даалгавар 1 · 30 мин

    Үлдсэн ажлын үргэлжлэх хугацаа ба логик

    Үр дүн
    The remaining work as a network
    Баримт бичиг
    Quantities, crew outputs, the elevator quote
    ERP дээр
    Schedule
  2. The update

    Даалгавар 2 · 30 мин

    Критик зам, нөөц хугацаа ба төлөвлөсөн дуусгалт

    Үр дүн
    Critical path, planned length, and the elevator's float (spare time)
    Баримт бичиг
    The update for the project manager
    ERP дээр
    Schedule, Critical Path
  3. Owner changes

    Даалгавар 3 · 30 мин

    Критик замаас гадуурх захиалагчийн өөрчлөлт

    Үр дүн
    Float used by CO-05, and the extension if any
    Баримт бичиг
    Change Order CO-05, storefront glass
    ERP дээр
    Schedule
  4. Owner changes

    Даалгавар 4 · 35 мин

    Критик замын захиалагчийн өөрчлөлт: фрагнет

    Үр дүн
    The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
    Баримт бичиг
    Change Order CO-03, quartz countertops
    ERP дээр
    Schedule
  5. Weather

    Даалгавар 5 · 40 мин

    Ердийн бус цаг агаар ба зэрэгцээ хоцролт

    Үр дүн
    The weather extension, apart from your own delay
    Баримт бичиг
    Daily reports and weather normals
    ERP дээр
    Schedule

How an event becomes days on the contract

Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.

Critical path
Даалгавар 2Planned lengthThe longest path sets the finish. Shorter paths carry float.
Same finish
Даалгавар 3CO-05The change spends float. The finish does not move.
CO-03Planned length
Даалгавар 4CO-03A fragnet, the change drawn as a small network, on the critical path moves the finish day for day.
WeatherCO-03Planned length
Даалгавар 5WeatherAbnormal days, less the float left, earn time. Your own delay earns none.

Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.

Товчхондоо. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.