CPM график жана мөөнөттү узартуу (АКШ, AIA A201)

You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.

1-тапшырманы баштоо

The site: a three-storey mixed-use building with a concrete retail podium and wood-frame apartment floors above.Ойдон чыгарылган долбоор
Quillfield CommonsMixed-use building, retail and apartments
Building
Three storeys: retail on a concrete podium, two floors of wood-frame apartments
Contract
AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
Story
Schedule update, February to May 2027
ERPдеги иш
Тапшырмалар: 5, болжол менен 2 саат 45 мүн

Ким кимге эмне берет

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Сизге келет

  • Elevator subcontractorQuotes the installation
    • Quote in weeks1-тапшырма
  • The ownerOwner, signs change orders
    • CO-053-тапшырма
    • CO-034-тапшырма
  • SuperintendentYour firm, keeps the daily reports
    • Daily reports5-тапшырма
СизProject scheduler, general contractor

Сизден кетет

    • Schedule update1-тапшырма
    • Critical path2-тапшырма
    Project managerYour firm, signs the update
    • CO-05 time analysis3-тапшырма
    • CO-03 fragnet4-тапшырма
    • Weather claim5-тапшырма
    ArchitectDecides extensions under A201

Долбоор боюнча жолуңуз

Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.

  1. The update

    1-тапшырма · 30 мүн

    Калган иштердин узактыгы жана логикасы

    Натыйжа
    The remaining work as a network
    Документ
    Quantities, crew outputs, the elevator quote
    ERPде
    Schedule
  2. The update

    2-тапшырма · 30 мүн

    Критикалык жол, запас жана пландалган аяктоо

    Натыйжа
    Critical path, planned length, and the elevator's float (spare time)
    Документ
    The update for the project manager
    ERPде
    Schedule, Critical Path
  3. Owner changes

    3-тапшырма · 30 мүн

    Критикалык жолдон тышкаркы ээсинин өзгөртүүсү

    Натыйжа
    Float used by CO-05, and the extension if any
    Документ
    Change Order CO-05, storefront glass
    ERPде
    Schedule
  4. Owner changes

    4-тапшырма · 35 мүн

    Критикалык жолдогу ээсинин өзгөртүүсү: фрагнет

    Натыйжа
    The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
    Документ
    Change Order CO-03, quartz countertops
    ERPде
    Schedule
  5. Weather

    5-тапшырма · 40 мүн

    Адаттан тыш аба ырайы жана параллелдүү кечигүү

    Натыйжа
    The weather extension, apart from your own delay
    Документ
    Daily reports and weather normals
    ERPде
    Schedule

How an event becomes days on the contract

Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.

Critical path
2-тапшырмаPlanned lengthThe longest path sets the finish. Shorter paths carry float.
Same finish
3-тапшырмаCO-05The change spends float. The finish does not move.
CO-03Planned length
4-тапшырмаCO-03A fragnet, the change drawn as a small network, on the critical path moves the finish day for day.
WeatherCO-03Planned length
5-тапшырмаWeatherAbnormal days, less the float left, earn time. Your own delay earns none.

Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.

Кыскача. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.