Курска киришүү · 3 мүн
CPM график жана мөөнөттү узартуу (АКШ, AIA A201)
You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.
Ойдон чыгарылган долбоор- Building
- Three storeys: retail on a concrete podium, two floors of wood-frame apartments
- Contract
- AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
- Story
- Schedule update, February to May 2027
- ERPдеги иш
- Тапшырмалар: 5, болжол менен 2 саат 45 мүн
Ким кимге эмне берет
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Сизге келет
- Elevator subcontractorQuotes the installation
- Quote in weeks1-тапшырма
- The ownerOwner, signs change orders
- CO-053-тапшырма
- CO-034-тапшырма
- SuperintendentYour firm, keeps the daily reports
- Daily reports5-тапшырма
Сизден кетет
- Schedule update1-тапшырма
- Critical path2-тапшырма
- CO-05 time analysis3-тапшырма
- CO-03 fragnet4-тапшырма
- Weather claim5-тапшырма
Долбоор боюнча жолуңуз
Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.
The update
1-тапшырма · 30 мүн
Калган иштердин узактыгы жана логикасы
- Натыйжа
- The remaining work as a network
- Документ
- Quantities, crew outputs, the elevator quote
- ERPде
- Schedule
The update
2-тапшырма · 30 мүн
Критикалык жол, запас жана пландалган аяктоо
- Натыйжа
- Critical path, planned length, and the elevator's float (spare time)
- Документ
- The update for the project manager
- ERPде
- Schedule, Critical Path
Owner changes
3-тапшырма · 30 мүн
Критикалык жолдон тышкаркы ээсинин өзгөртүүсү
- Натыйжа
- Float used by CO-05, and the extension if any
- Документ
- Change Order CO-05, storefront glass
- ERPде
- Schedule
Owner changes
4-тапшырма · 35 мүн
Критикалык жолдогу ээсинин өзгөртүүсү: фрагнет
- Натыйжа
- The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
- Документ
- Change Order CO-03, quartz countertops
- ERPде
- Schedule
Weather
5-тапшырма · 40 мүн
Адаттан тыш аба ырайы жана параллелдүү кечигүү
- Натыйжа
- The weather extension, apart from your own delay
- Документ
- Daily reports and weather normals
- ERPде
- Schedule
How an event becomes days on the contract
Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.
Көк менен — тапшырма кошкон бөлүк; боз менен — мурунку кадамдан келгени.
Кыскача. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.