Introduksjon til kurset · 3 min
CPM-fremdriftsplan og fristforlengelse (USA, AIA A201)
You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.
Fiktivt prosjekt- Building
- Three storeys: retail on a concrete podium, two floors of wood-frame apartments
- Contract
- AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
- Story
- Schedule update, February to May 2027
- Arbeid i ERP
- 5 oppgaver, omtrent 2 t 45 min
Hvem gir hva til hvem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer til deg
- Elevator subcontractorQuotes the installation
- Quote in weeksOppgave 1
- The ownerOwner, signs change orders
- CO-05Oppgave 3
- CO-03Oppgave 4
- SuperintendentYour firm, keeps the daily reports
- Daily reportsOppgave 5
Går fra deg
- Schedule updateOppgave 1
- Critical pathOppgave 2
- CO-05 time analysisOppgave 3
- CO-03 fragnetOppgave 4
- Weather claimOppgave 5
Din vei gjennom prosjektet
Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.
The update
Oppgave 1 · 30 min
Varigheter og logikk for gjenstående arbeid
- Du leverer
- The remaining work as a network
- Dokument
- Quantities, crew outputs, the elevator quote
- I ERP
- Schedule
The update
Oppgave 2 · 30 min
Kritisk linje, slakk og planlagt ferdigstillelse
- Du leverer
- Critical path, planned length, and the elevator's float (spare time)
- Dokument
- The update for the project manager
- I ERP
- Schedule, Critical Path
Owner changes
Oppgave 3 · 30 min
En endring fra byggherren utenfor den kritiske linjen
- Du leverer
- Float used by CO-05, and the extension if any
- Dokument
- Change Order CO-05, storefront glass
- I ERP
- Schedule
Owner changes
Oppgave 4 · 35 min
En endring fra byggherren på den kritiske linjen: fragnettet
- Du leverer
- The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
- Dokument
- Change Order CO-03, quartz countertops
- I ERP
- Schedule
Weather
Oppgave 5 · 40 min
Unormalt vær og samtidig forsinkelse
- Du leverer
- The weather extension, apart from your own delay
- Dokument
- Daily reports and weather normals
- I ERP
- Schedule
How an event becomes days on the contract
Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.
Blått er det oppgaven legger til; grått er overført fra før.
Kort sagt. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.