Inleiding tot de cursus · 3 min

CPM-planning en termijnverlengingen (VS, AIA A201)

You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.

Start opdracht 1

The site: a three-storey mixed-use building with a concrete retail podium and wood-frame apartment floors above.Fictief project
Quillfield CommonsMixed-use building, retail and apartments
Building
Three storeys: retail on a concrete podium, two floors of wood-frame apartments
Contract
AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
Story
Schedule update, February to May 2027
Werk in de ERP
5 opdrachten, ongeveer 2 u 45 min

Wie geeft wat aan wie

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Komt bij u

  • Elevator subcontractorQuotes the installation
    • Quote in weeksOpdracht 1
  • The ownerOwner, signs change orders
    • CO-05Opdracht 3
    • CO-03Opdracht 4
  • SuperintendentYour firm, keeps the daily reports
    • Daily reportsOpdracht 5
UProject scheduler, general contractor

Gaat van u uit

    • Schedule updateOpdracht 1
    • Critical pathOpdracht 2
    Project managerYour firm, signs the update
    • CO-05 time analysisOpdracht 3
    • CO-03 fragnetOpdracht 4
    • Weather claimOpdracht 5
    ArchitectDecides extensions under A201

Uw route door het project

Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.

  1. The update

    Opdracht 1 · 30 min

    Duren en logica van het resterende werk

    U levert
    The remaining work as a network
    Document
    Quantities, crew outputs, the elevator quote
    In de ERP
    Schedule
  2. The update

    Opdracht 2 · 30 min

    Kritiek pad, speling en de geplande oplevering

    U levert
    Critical path, planned length, and the elevator's float (spare time)
    Document
    The update for the project manager
    In de ERP
    Schedule, Critical Path
  3. Owner changes

    Opdracht 3 · 30 min

    Een wijziging van de opdrachtgever buiten het kritieke pad

    U levert
    Float used by CO-05, and the extension if any
    Document
    Change Order CO-05, storefront glass
    In de ERP
    Schedule
  4. Owner changes

    Opdracht 4 · 35 min

    Een wijziging van de opdrachtgever op het kritieke pad: het fragnet

    U levert
    The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
    Document
    Change Order CO-03, quartz countertops
    In de ERP
    Schedule
  5. Weather

    Opdracht 5 · 40 min

    Abnormaal weer en gelijktijdige vertraging

    U levert
    The weather extension, apart from your own delay
    Document
    Daily reports and weather normals
    In de ERP
    Schedule

How an event becomes days on the contract

Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.

Critical path
Opdracht 2Planned lengthThe longest path sets the finish. Shorter paths carry float.
Same finish
Opdracht 3CO-05The change spends float. The finish does not move.
CO-03Planned length
Opdracht 4CO-03A fragnet, the change drawn as a small network, on the critical path moves the finish day for day.
WeatherCO-03Planned length
Opdracht 5WeatherAbnormal days, less the float left, earn time. Your own delay earns none.

Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.

Kort gezegd. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.