Kurssin johdanto · 3 min

CPM-aikataulu ja määräajan pidennykset (USA, AIA A201)

You are the general contractor's scheduler on a three-storey building: you plan when each piece of work happens. The owner has asked for changes, and the weather was bad. In five tasks, in the Schedule module, you rebuild the remaining work as a network of linked activities, find the critical path (the chain that sets the finish), and work out how many days the owner's changes and the weather earn.

Aloita tehtävä 1

The site: a three-storey mixed-use building with a concrete retail podium and wood-frame apartment floors above.Kuvitteellinen hanke
Quillfield CommonsMixed-use building, retail and apartments
Building
Three storeys: retail on a concrete podium, two floors of wood-frame apartments
Contract
AIA A101-2017 stipulated sum (one fixed price) with A201-2017 general conditions
Story
Schedule update, February to May 2027
Työ ERP:ssä
Tehtäviä 5, noin 2 t 45 min

Kuka antaa mitä kenelle

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tulee sinulle

  • Elevator subcontractorQuotes the installation
    • Quote in weeksTehtävä 1
  • The ownerOwner, signs change orders
    • CO-05Tehtävä 3
    • CO-03Tehtävä 4
  • SuperintendentYour firm, keeps the daily reports
    • Daily reportsTehtävä 5
SinäProject scheduler, general contractor

Lähtee sinulta

    • Schedule updateTehtävä 1
    • Critical pathTehtävä 2
    Project managerYour firm, signs the update
    • CO-05 time analysisTehtävä 3
    • CO-03 fragnetTehtävä 4
    • Weather claimTehtävä 5
    ArchitectDecides extensions under A201

Reittisi hankkeen läpi

Two tasks build the update, two test owner changes against it, one weighs the weather. Start with task 1: in Schedule you work out durations from quantities and crew outputs and link the remaining work.

  1. The update

    Tehtävä 1 · 30 min

    Jäljellä olevan työn kestot ja logiikka

    Tuotat
    The remaining work as a network
    Asiakirja
    Quantities, crew outputs, the elevator quote
    ERP:ssä
    Schedule
  2. The update

    Tehtävä 2 · 30 min

    Kriittinen polku, väljä ja suunniteltu valmistuminen

    Tuotat
    Critical path, planned length, and the elevator's float (spare time)
    Asiakirja
    The update for the project manager
    ERP:ssä
    Schedule, Critical Path
  3. Owner changes

    Tehtävä 3 · 30 min

    Omistajan muutos kriittisen polun ulkopuolella

    Tuotat
    Float used by CO-05, and the extension if any
    Asiakirja
    Change Order CO-05, storefront glass
    ERP:ssä
    Schedule
  4. Owner changes

    Tehtävä 4 · 35 min

    Omistajan muutos kriittisellä polulla: fragnet

    Tuotat
    The CO-03 fragnet (the change drawn as a small network) and its extension in calendar days
    Asiakirja
    Change Order CO-03, quartz countertops
    ERP:ssä
    Schedule
  5. Weather

    Tehtävä 5 · 40 min

    Poikkeuksellinen sää ja samanaikainen viive

    Tuotat
    The weather extension, apart from your own delay
    Asiakirja
    Daily reports and weather normals
    ERP:ssä
    Schedule

How an event becomes days on the contract

Each column is the time to Substantial Completion, when the owner can use the building, after one task. Task 1 builds the durations they all stand on.

Critical path
Tehtävä 2Planned lengthThe longest path sets the finish. Shorter paths carry float.
Same finish
Tehtävä 3CO-05The change spends float. The finish does not move.
CO-03Planned length
Tehtävä 4CO-03A fragnet, the change drawn as a small network, on the critical path moves the finish day for day.
WeatherCO-03Planned length
Tehtävä 5WeatherAbnormal days, less the float left, earn time. Your own delay earns none.

Sininen on se, mitä tehtävä lisää; harmaa tulee aiemmasta.

Lyhyesti. Time follows the finish, not the activity. Measure each event on the current update, and state the extension in calendar days.