OpenConstruction Academy
התחברות / הרשמה
HE

תיאוריה לפני משימה 2 · 9 דק׳

Pricing the building element by element

תכנית העלויות האלמנטלית

אחרי ההרצאה הזו תוכלו

  1. Name the NRM 1 group elements and what each is measured on.
  2. Pick the right element unit quantity for substructure and upper floors.
  3. Check the elemental plan against the order of cost, per m² GIFA, as a percentage.
1 / 4

Top-down, then bottom-up

The order of cost priced the building as one thing. The elemental cost plan prices it as parts: the ground it stands on, its frame, its floors and walls, its finishes, its services. Each part has its own quantity and its own rate. When both ways agree, the client can trust the number. When they do not, the difference tells you where to look.

דוגמה. The benchmark line was a check. Once the elements are priced, it has done its job and comes out of the bill. Left in, it prices the building twice.
2 / 4

The NRM 1 group elements

NRM 1 sorts building works into numbered groups, so that every cost plan reads the same way and can be compared with others. Substructure is the foundations and the lowest floor; superstructure is the frame, upper floors, roof, walls, windows and doors; services are heating, power, lifts and drainage. Preliminaries, overheads and profit, fees, risk and inflation follow as groups of their own.

דוגמה. In this course groups 6 and 7 are nil and group 0 is held by the client, so the plan prices groups 1 to 5 and 8.
Facilitating worksGroup 0
SubstructureGroup 1
SuperstructureGroup 2
Internal finishesGroup 3
Fittings, furnishings and equipmentGroup 4
ServicesGroup 5
Prefabricated buildingsGroup 6
Work to existing buildingsGroup 7
External worksGroup 8
3 / 4

Each element has its own measure

An element unit quantity is what the element is priced on. Substructure is priced on the area of the lowest floor: its rate already covers the foundations under the whole building. Upper floors are the floors above the lowest one. Frame, finishes and most services are priced per m² of GIFA. Walls and roofs have their own areas.

דוגמה. For a building of 1,500.00 m² GIFA whose lowest floor is 800.00 m², the three measures are 800.00 m², 700 m² and 1,500.00 m². Swap the first two and the substructure is priced on the wrong floor.
Substructure: lowest floor
800
Upper floors: floors above the lowest
700
Frame, finishes, services: GIFA
1,500
4 / 4

The cost check

Add the elements to a direct cost and divide by GIFA. That rate is comparable with the order of cost rate, because both are per m² GIFA at the same base date. Report the difference as a percentage of the order of cost: elemental less order of cost, divided by order of cost. Below the benchmark is negative.

דוגמה. Divide by the footprint and the rate looks three times too high. Divide by the net internal area and it looks too high again. Only GIFA gives a figure the benchmark can be compared with.

Price a clinic by its elements

A different building from your task, with its elements simplified to three lines. Predict each figure first.

לא בקנה מידה
הבעיה
  • GIFA 1,200.00 m². The lowest floor is 650.00 m².
  • Substructure £320.00 per m² of lowest floor. Upper floors £160.00 per m². Everything else together £2,700.00 per m² GIFA.
  • The order of cost estimate was £3,000.00 per m² GIFA at the same base date.
Lowest floor: substructure
650
Upper floors
?
Lowest floor: substructure
650
Upper floors
550
שלב 1 מתוך 4

Upper floors quantity

The floors above the lowest one. What quantity goes on the upper floors line?

1,200.00 m² − 650.00 m² = 550.00 m². The lowest floor belongs to the substructure, not to the upper floors.

???
  • Substructure ?
  • Upper floors ?
  • Everything else ?
£3,240,000
  • Substructure £208,000
  • Upper floors £88,000
  • Everything else £3,240,000
שלב 2 מתוך 4

Direct cost

Each line is its quantity times its rate. What is the direct cost of the three lines?

Substructure 650.00 m² × £320.00 = £208,000. Upper floors 550.00 m² × £160.00 = £88,000. The rest 1,200.00 m² × £2,700.00 = £3,240,000. Direct cost £3,536,000.

Direct cost£3,536,000
GIFA1,200.00 m²
Per m² GIFA?
Direct cost£3,536,000
GIFA1,200.00 m²
Per m² GIFA£2,946.67
שלב 3 מתוך 4

Cost per m² GIFA

Direct cost divided by GIFA. Give pence.

£3,536,000 ÷ 1,200.00 m² = £2,946.67 per m² GIFA.

Order of cost, per m²
£3,000
Elemental, per m²
£2,947
Order of cost, per m²
£3,000
Elemental, per m²
£2,947
שלב 4 מתוך 4

Against the order of cost

Elemental less order of cost, as a percentage of the order of cost. Two decimals.

(£2,946.67 − £3,000.00) ÷ £3,000.00 × 100 = -1.78%. The elements land close to the benchmark, a little below it.

בקצרה. Each element on its own measure, summed to a direct cost, divided by GIFA, compared with the order of cost as a signed percentage.

בדקו את עצמכם

שאלה 1 מתוך 3

Substructure in a three-storey building. Which quantity is it priced on?

  • The substructure rate covers the foundations under the whole building, so it is applied to the lowest floor once.

  • That prices the foundations three times over.

  • That is the measure for upper floors, a different element.

שאלה 2 מתוך 3

The elemental plan comes to £3,150.00 per m² GIFA. The order of cost was £3,000.00 per m² GIFA. What is the difference, as a percentage of the order of cost?

(3,150.00 − 3,000.00) ÷ 3,000.00 × 100 = 5%.
שאלה 3 מתוך 3

The order of cost line is still in the bill next to the elements. What happens to the direct cost?

  • The software adds every line in the bill. A reference line left in is priced.

  • Delete the benchmark line once the elements replace it. Keep its rate for the cost check.

  • It becomes meaningless: the direct cost is roughly double.