OpenConstruction Academy
Prijava / Registracija
HR

Teorija prije zadatka 3 · 11 min

Which delay moves completion? The critical path and float

Koje kašnjenje pomiče Dovršetak? Kritični put

Nakon ovog predavanja moći ćete

  1. Find the critical path of a small network: the longest chain of dependent activities.
  2. Compute total float and say why a delay within float does not move completion.
  3. Size the extension of time a delay to a critical activity justifies.
1 / 3

Extension of time needs delay to completion

Sub-Clause 8.5 of FIDIC 2017 gives an extension of the Time for Completion when completion is or will be delayed by a listed cause, such as late drawings under Sub-Clause 1.9 or unforeseeable physical conditions. The test is the date of completion, not the activity: a delay that the programme can absorb gives no extension. That is decided on the programme, with the critical path method.

Primjer. Delayed work and delayed completion are not the same thing.
2 / 3

Critical path and float

Each activity has a duration and predecessors. The longest chain from start to finish is the critical path; its length is the project duration. Any other activity has total float: the time it can slip without moving completion. Float of an activity = latest start − earliest start.

Primjer. A 10 days, then B 17 and C 10 in parallel, then D 5. A–B–D takes 32 days; C has 17 − 10 = 7 days of float.
A, B, D (critical)
SAR 32 (SAR 10 + SAR 17 + SAR 5)
A, C, D
SAR 25 (SAR 10 + SAR 10 + SAR 5)
3 / 3

How much extension

A delay to a critical activity moves completion day for day. A delay to a non-critical activity moves completion only by the part that exceeds its float. Two delays at the same time are not added: check each against the programme, and the one that drives completion decides.

Primjer. A 5-day delay to C (float 7) moves nothing. A 12-day delay to C moves completion by 5 days.

Two delays, one programme

A small programme: A 10 days, then B 17 and C 10 in parallel, then D 5. Late drawings delay C by 12 days.

Nije u mjerilu
Zadatak
  • A (10 days) comes first. B (17 days) and C (10 days) both follow A. D (5 days) follows both B and C.
  • Late drawings delay C by 12 days. Nothing else is late.
A, B, D
SAR 32 (SAR 10 + SAR 17 + SAR 5)
A, C, D
SAR 25 (SAR 10 + SAR 10 + SAR 5)
A, B, D
SAR 32 (SAR 10 + SAR 17 + SAR 5)
A, C, D
SAR 25 (SAR 10 + SAR 10 + SAR 5)
Korak 1 od 3

Project duration

The longest chain. How many days?

10 + 17 + 5 = 32 days.

Korak 2 od 3

Float of C

How long can C slip without moving completion?

17 − 10 = 7 days.

Korak 3 od 3

Extension of time

C is delayed 12 days. By how many days does completion move?

12 − 7 = 5 days.

Ukratko. Find the longest chain, compute float for the rest. A delay counts only as far as it moves completion.

Provjerite se

Pitanje 1 od 3

An activity with 18 days of total float is delayed by 25 days. How many days does completion move?

25 − 18 = 7 days.
Pitanje 2 od 3

A delay hits an activity with 60 days of float. It lasts 18 days. What extension does it justify?

  • It is absorbed by float.

  • Right.

  • Float is not an entitlement.

Pitanje 3 od 3

Two delays run at the same time: one on a critical activity, one within float. What decides the extension?

  • Delays are tested against the programme, not added.

  • Right.

  • The critical one still moves completion.