OpenConstruction Academy
Нэвтрэх / Бүртгүүлэх
MN

1-р даалгаврын өмнөх онол · 11 мин

K3: from collective wage to the crew's hourly cost

K3: бригадын цагийн ханш

Сургалтын танилцуулга

Энэ лекцийн дараа та дараахыг хийж чадна

  1. Read the K3 sheet of ÖNORM B 2061 line by line: B10, payroll extras, B15, PGK, B18.
  2. Round each line to the cent, as the sheet does, and get the Mittellohnkosten.
  3. Price a labour-only item as hours per unit times the hourly cost.
1 / 3

Why Austria prices labour on a form

In Austrian public works, prices must be explainable. Under the Federal Procurement Act (BVergG 2018, § 137) a client can examine a bid in depth and ask how each price was built. ÖNORM B 2061 gives the forms for that: K3 builds the hourly labour rate of a crew, K4 the price of a material on site, K2 the overall surcharge, K7 the price of an item. A rate that cannot be traced through these sheets is hard to defend.

Жишээ. This lecture covers K3. Its result, B18, is a cost; B21 adds the surcharge and is a price.
2 / 3

The K3 lines

B10 is the wage subject to payroll charges: the collective agreement (KV) wage of the crew, weighted by its members, plus overpayment (AKV), allowances and overtime premiums. B11 adds payments not subject to charges, such as a daily allowance (Taggeld). B12 and B13 are the direct and the allocated payroll extras (DPNK, UPNK) in percent of B10: employer's contributions, paid holidays, public holidays, severance. B14 is any further extra per hour. B15 is the sum. B16, the personnel overheads (PGK), is a percentage of B15. B18 = B15 + B16, the Mittellohnkosten.

Жишээ. B10 21.40 €/h with DPNK 28.74 % and UPNK 75 %: B12 = 6.15 and B13 = 16.05 €/h.
B10 wage subject to charges€21.40
B11 Taggeld€1.20
B12 DPNK 28.74 %€6.15
B13 UPNK 75 %€16.05
B14 further extras€0.10
B15€44.90
3 / 3

Hours times the rate

An item priced on labour alone, such as hand excavation or demolition, costs its time value (hours per unit, from the firm's own records) times B18. Whether the bill of quantities carries costs or prices decides which rate goes in: B18 for a cost calculation, B21 for a price. Mixing the two is the commonest error on a K7.

Жишээ. 1.80 h/m³ at 48.04 €/h is 86.47 €/m³ at cost.

Build a crew's hourly cost

A crew's weighted wage subject to charges is known. Complete the K3 to B18 and price a labour-only item at cost.

Масштабгүй
Бодлого
  • B10 €21.40 per hour. B11 Taggeld €1.20, not subject to charges. B14 €0.10.
  • DPNK 28.74 %, UPNK 75.00 % of B10. PGK 7.00 % of B15. Round every line to the cent.
  • Item: hand excavation, 1.8 h/m³.
Алхам 1 / 4

Payroll extras

B12 + B13, each rounded. What are the payroll extras per hour?

€21.40 × 28.74 % = €6.15; €21.40 × 75 % = €16.05; together €22.20.

€21.40€22.20
  • B10 €21.40
  • B11 €1.20
  • B12 + B13 €22.20
  • B14 €0.10
€21.40€22.20
  • B10 €21.40
  • B11 €1.20
  • B12 + B13 €22.20
  • B14 €0.10
Алхам 2 / 4

B15

B10 + B11 + B12 + B13 + B14. What is B15?

€21.40 + €1.20 + €22.20 + €0.10 = €44.90.

Алхам 3 / 4

B18 Mittellohnkosten

Add PGK, 7 % of B15, rounded. What is B18?

€44.90 + €3.14 = €48.04 per hour.

Алхам 4 / 4

Item at cost

1.80 h/m³ times B18. What is the unit cost?

1.8 × €48.04 = €86.47 per m³.

Товчхондоо. B10 is the base; payroll extras ride on B10, PGK on B15. B18 is the crew's cost per hour, and labour items are hours times B18.

Өөрийгөө шалгах

Асуулт 1 / 3

B15 is 46.00 €/h and PGK is 7.50 %. What is B18?

46.00 + 3.45 = €49.45 per hour.
Асуулт 2 / 3

On what base are the payroll extras DPNK and UPNK taken?

  • Right.

  • B15 already contains them; PGK is the one taken on B15.

  • Overpayment and allowances are also subject to charges, so they are in B10.

Асуулт 3 / 3

The bill of quantities is priced at cost. Which hourly rate goes into a labour-only item?

  • B21 includes the surcharge; that is a price.

  • Right.

  • B10 lacks payroll extras and PGK.