ÖNORM B 2061 дагуу зардал тооцоо: K3, K7 ба нэмэлт зардлын нэхэмжлэл
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
Зохиомол төсөл- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- ERP дээрх ажил
- Даалгавар: 5, ойролцоогоор 3 цаг 5 мин
Хэн хэнд юу дамжуулдаг
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Танд ирдэг
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage linesДаалгавар 1
- Wall item 03.01 without a priceДаалгавар 2
- Contract terms for the retentionsДаалгавар 4
- ÖBASite supervision, orders and checks
- Order for sound-insulating wallsДаалгавар 3
- Measured progress to end of AugustДаалгавар 4
Танаас гардаг
- Hourly rate on K3 and wage lines in the billДаалгавар 1
- K7 price with the surcharges on K2Даалгавар 2
- Additional-cost claim (Nachtrag)Даалгавар 3
- Interim invoice (Abschlagsrechnung) with cover retentionДаалгавар 4
- Final invoice (Schlussrechnung) with warranty retentionДаалгавар 5
Төслөөр явах таны зам
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
Даалгавар 1 · 30 мин
K3: бригадын цагийн ханш
- Үр дүн
- Hourly rate of the crew from K3, entered on the wage lines
- Баримт бичиг
- K3 inputs and the bill (LV)
- ERP дээр
- Bill of Quantities
Build the price
Даалгавар 2 · 35 мин
K7 ба K2: нэмэгдэл зөв суурь дээр
- Үр дүн
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- Баримт бичиг
- K2, K4 material price, time per m²
- ERP дээр
- Bill of Quantities
Price the change
Даалгавар 3 · 40 мин
ÖNORM B 2110 дагуух нэмэлт зардлын нэхэмжлэл
- Үр дүн
- New unit price and the additional cost, filed as a claim
- Баримт бичиг
- The site supervisor's (ÖBA) order and the tender price basis
- ERP дээр
- Variations
Invoice
Даалгавар 4 · 40 мин
Барьцаатай завсрын нэхэмжлэл
- Үр дүн
- Interim invoice 1 and the amount payable
- Баримт бичиг
- Measured progress and the contract terms
- ERP дээр
- Contracts
Invoice
Даалгавар 5 · 40 мин
Эцсийн нэхэмжлэл ба гарантийн барьцаа
- Үр дүн
- Final invoice, warranty retention and the remaining payment
- Баримт бичиг
- Contract sum, agreed claim, interim payment
- ERP дээр
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.
Товчхондоо. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.