معرفی دوره · 3 دقیقه
برآورد بر اساس ÖNORM B 2061: K3، K7 و ادعای هزینههای اضافی
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
پروژهٔ خیالی- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- کار در ERP
- 5 تکلیف، حدود 3 ساعت 5 دقیقه
چه کسی چه چیزی به چه کسی میدهد
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
به شما میرسد
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage linesتکلیف 1
- Wall item 03.01 without a priceتکلیف 2
- Contract terms for the retentionsتکلیف 4
- ÖBASite supervision, orders and checks
- Order for sound-insulating wallsتکلیف 3
- Measured progress to end of Augustتکلیف 4
از شما میرود
- Hourly rate on K3 and wage lines in the billتکلیف 1
- K7 price with the surcharges on K2تکلیف 2
- Additional-cost claim (Nachtrag)تکلیف 3
- Interim invoice (Abschlagsrechnung) with cover retentionتکلیف 4
- Final invoice (Schlussrechnung) with warranty retentionتکلیف 5
مسیر شما در پروژه
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
تکلیف 1 · 30 دقیقه
K3: نرخ ساعتی اکیپ کاری
- خروجی شما
- Hourly rate of the crew from K3, entered on the wage lines
- سند
- K3 inputs and the bill (LV)
- در ERP
- Bill of Quantities
Build the price
تکلیف 2 · 35 دقیقه
K7 و K2: ضرایب روی مبنای درست
- خروجی شما
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- سند
- K2, K4 material price, time per m²
- در ERP
- Bill of Quantities
Price the change
تکلیف 3 · 40 دقیقه
ادعای هزینههای اضافی طبق ÖNORM B 2110
- خروجی شما
- New unit price and the additional cost, filed as a claim
- سند
- The site supervisor's (ÖBA) order and the tender price basis
- در ERP
- Variations
Invoice
تکلیف 4 · 40 دقیقه
صورتحساب موقت با تضمین پوششی (Deckungsrücklass)
- خروجی شما
- Interim invoice 1 and the amount payable
- سند
- Measured progress and the contract terms
- در ERP
- Contracts
Invoice
تکلیف 5 · 40 دقیقه
صورتحساب نهایی و تضمین عیوب
- خروجی شما
- Final invoice, warranty retention and the remaining payment
- سند
- Contract sum, agreed claim, interim payment
- در ERP
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
آبی چیزی است که تکلیف اضافه میکند؛ خاکستری از مرحلهٔ قبل آمده است.
بهطور خلاصه. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.