Kurssin johdanto · 3 min
Kustannuslaskenta ÖNORM B 2061 -standardin mukaan: K3, K7 ja lisäkustannusvaatimus
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
Kuvitteellinen hanke- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- Työ ERP:ssä
- Tehtäviä 5, noin 3 t 5 min
Kuka antaa mitä kenelle
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tulee sinulle
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage linesTehtävä 1
- Wall item 03.01 without a priceTehtävä 2
- Contract terms for the retentionsTehtävä 4
- ÖBASite supervision, orders and checks
- Order for sound-insulating wallsTehtävä 3
- Measured progress to end of AugustTehtävä 4
Lähtee sinulta
- Hourly rate on K3 and wage lines in the billTehtävä 1
- K7 price with the surcharges on K2Tehtävä 2
- Additional-cost claim (Nachtrag)Tehtävä 3
- Interim invoice (Abschlagsrechnung) with cover retentionTehtävä 4
- Final invoice (Schlussrechnung) with warranty retentionTehtävä 5
Reittisi hankkeen läpi
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
Tehtävä 1 · 30 min
K3: työryhmän tuntihinta
- Tuotat
- Hourly rate of the crew from K3, entered on the wage lines
- Asiakirja
- K3 inputs and the bill (LV)
- ERP:ssä
- Bill of Quantities
Build the price
Tehtävä 2 · 35 min
K7 ja K2: lisät oikealle perusteelle
- Tuotat
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- Asiakirja
- K2, K4 material price, time per m²
- ERP:ssä
- Bill of Quantities
Price the change
Tehtävä 3 · 40 min
Lisäkustannusvaatimus (Mehrkostenforderung) ÖNORM B 2110 -standardin mukaan
- Tuotat
- New unit price and the additional cost, filed as a claim
- Asiakirja
- The site supervisor's (ÖBA) order and the tender price basis
- ERP:ssä
- Variations
Invoice
Tehtävä 4 · 40 min
Väliaikalasku (Abschlagsrechnung) katepidätyksellä
- Tuotat
- Interim invoice 1 and the amount payable
- Asiakirja
- Measured progress and the contract terms
- ERP:ssä
- Contracts
Invoice
Tehtävä 5 · 40 min
Loppulasku ja takuupidätys (Haftrücklass)
- Tuotat
- Final invoice, warranty retention and the remaining payment
- Asiakirja
- Contract sum, agreed claim, interim payment
- ERP:ssä
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
Sininen on se, mitä tehtävä lisää; harmaa tulee aiemmasta.
Lyhyesti. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.