Kurssin johdanto · 3 min

Kustannuslaskenta ÖNORM B 2061 -standardin mukaan: K3, K7 ja lisäkustannusvaatimus

You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.

Aloita tehtävä 1

A multi-storey concrete frame under construction against a blue sky, with timber formwork and an orange scaffold platform on the upper floor, scaffolding below and glazed openings on the right.Kuvitteellinen hanke
Volksschule Lindenau, ZubauPrimary school extension · concrete frame with formwork
Building
School extension with two classrooms and a group room, brick walls and concrete slab
Contract
Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
Calculation
ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
Työ ERP:ssä
Tehtäviä 5, noin 3 t 5 min

Kuka antaa mitä kenelle

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tulee sinulle

  • The municipalityClient (Auftraggeberin), pays
    • Bill of quantities (LV) with unpriced wage linesTehtävä 1
    • Wall item 03.01 without a priceTehtävä 2
    • Contract terms for the retentionsTehtävä 4
  • ÖBASite supervision, orders and checks
    • Order for sound-insulating wallsTehtävä 3
    • Measured progress to end of AugustTehtävä 4
SinäKalkulant, contractor

Lähtee sinulta

    • Hourly rate on K3 and wage lines in the billTehtävä 1
    • K7 price with the surcharges on K2Tehtävä 2
    • Additional-cost claim (Nachtrag)Tehtävä 3
    ÖBAReviews the claim and the invoices
    • Interim invoice (Abschlagsrechnung) with cover retentionTehtävä 4
    • Final invoice (Schlussrechnung) with warranty retentionTehtävä 5
    The municipalityReceives the invoices

Reittisi hankkeen läpi

Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.

  1. Build the price

    Tehtävä 1 · 30 min

    K3: työryhmän tuntihinta

    Tuotat
    Hourly rate of the crew from K3, entered on the wage lines
    Asiakirja
    K3 inputs and the bill (LV)
    ERP:ssä
    Bill of Quantities
  2. Build the price

    Tehtävä 2 · 35 min

    K7 ja K2: lisät oikealle perusteelle

    Tuotat
    K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
    Asiakirja
    K2, K4 material price, time per m²
    ERP:ssä
    Bill of Quantities
  3. Price the change

    Tehtävä 3 · 40 min

    Lisäkustannusvaatimus (Mehrkostenforderung) ÖNORM B 2110 -standardin mukaan

    Tuotat
    New unit price and the additional cost, filed as a claim
    Asiakirja
    The site supervisor's (ÖBA) order and the tender price basis
    ERP:ssä
    Variations
  4. Invoice

    Tehtävä 4 · 40 min

    Väliaikalasku (Abschlagsrechnung) katepidätyksellä

    Tuotat
    Interim invoice 1 and the amount payable
    Asiakirja
    Measured progress and the contract terms
    ERP:ssä
    Contracts
  5. Invoice

    Tehtävä 5 · 40 min

    Loppulasku ja takuupidätys (Haftrücklass)

    Tuotat
    Final invoice, warranty retention and the remaining payment
    Asiakirja
    Contract sum, agreed claim, interim payment
    ERP:ssä
    Contracts

From a wage to the final payment

Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.

Site costsEmployer's charges on the wageDaily allowance, no chargesWage with overpayment and allowances
Tehtävä 1K3: the crew's hourly costThe collective-agreement wage, then allowances, then the employer's charges on the wage subject to charges, then site costs, built up line by line.
Material from K4, loss includedRisk and profitFinancingOverheads (GGK)Hourly cost from K3
Tehtävä 2K2 and K7: surcharges in orderOverheads, financing, risk and profit are applied one after another, each on the sum so far. Added side by side on the base, they come out short.
Supplier's higher price todayMaterial at the tender price listLabour at the tender wage price
Tehtävä 3Additional-cost claimThe new price is built from the tender's price basis, not from today's market. Where the bill has no equal item, a comparable one gives the time.
Claim, still in reviewCover retentionNet amount payable
Tehtävä 4Interim invoiceMeasured progress at contract prices. The cover retention, a share held back as security, is taken from the net invoice. A claim still under review stays out.
Warranty retention (Haftrücklass)Paid on interim invoiceRemaining payment
Tehtävä 5Final invoiceContract sum plus the agreed claim, less the interim payment. The warranty retention comes from the final invoice amount, and the cover retention is released against it.

Sininen on se, mitä tehtävä lisää; harmaa tulee aiemmasta.

Lyhyesti. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.