Introducere în curs · 3 min
Calculația după ÖNORM B 2061: K3, K7 și o cerere de costuri suplimentare
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
Proiect fictiv- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- Lucru în ERP
- 5 sarcini, circa 3 h 5 min
Cine ce predă cui
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Ajunge la tine
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage linesSarcina 1
- Wall item 03.01 without a priceSarcina 2
- Contract terms for the retentionsSarcina 4
- ÖBASite supervision, orders and checks
- Order for sound-insulating wallsSarcina 3
- Measured progress to end of AugustSarcina 4
Pleacă de la tine
- Hourly rate on K3 and wage lines in the billSarcina 1
- K7 price with the surcharges on K2Sarcina 2
- Additional-cost claim (Nachtrag)Sarcina 3
- Interim invoice (Abschlagsrechnung) with cover retentionSarcina 4
- Final invoice (Schlussrechnung) with warranty retentionSarcina 5
Traseul tău prin proiect
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
Sarcina 1 · 30 min
K3: tariful orar al echipei
- Produci
- Hourly rate of the crew from K3, entered on the wage lines
- Document
- K3 inputs and the bill (LV)
- În ERP
- Bill of Quantities
Build the price
Sarcina 2 · 35 min
K7 și K2: adaosuri pe baza corectă
- Produci
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- Document
- K2, K4 material price, time per m²
- În ERP
- Bill of Quantities
Price the change
Sarcina 3 · 40 min
Cerere de costuri suplimentare după ÖNORM B 2110
- Produci
- New unit price and the additional cost, filed as a claim
- Document
- The site supervisor's (ÖBA) order and the tender price basis
- În ERP
- Variations
Invoice
Sarcina 4 · 40 min
Factură intermediară cu reținere de acoperire
- Produci
- Interim invoice 1 and the amount payable
- Document
- Measured progress and the contract terms
- În ERP
- Contracts
Invoice
Sarcina 5 · 40 min
Factura finală și reținerea pentru defecte
- Produci
- Final invoice, warranty retention and the remaining payment
- Document
- Contract sum, agreed claim, interim payment
- În ERP
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
Albastru este ce adaugă sarcina; gri este ce vine de dinainte.
Pe scurt. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.