Uvod u tečaj · 3 min
Kalkulacija prema ÖNORM B 2061: K3, K7 i zahtjev za dodatne troškove
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
Izmišljeni projekt- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- Rad u ERP-u
- Zadataka: 5, oko 3 h 5 min
Tko kome što predaje
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dolazi vama
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage linesZadatak 1
- Wall item 03.01 without a priceZadatak 2
- Contract terms for the retentionsZadatak 4
- ÖBASite supervision, orders and checks
- Order for sound-insulating wallsZadatak 3
- Measured progress to end of AugustZadatak 4
Odlazi od vas
- Hourly rate on K3 and wage lines in the billZadatak 1
- K7 price with the surcharges on K2Zadatak 2
- Additional-cost claim (Nachtrag)Zadatak 3
- Interim invoice (Abschlagsrechnung) with cover retentionZadatak 4
- Final invoice (Schlussrechnung) with warranty retentionZadatak 5
Vaš put kroz projekt
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
Zadatak 1 · 30 min
K3: satnica ekipe
- Vaš rezultat
- Hourly rate of the crew from K3, entered on the wage lines
- Dokument
- K3 inputs and the bill (LV)
- U ERP-u
- Bill of Quantities
Build the price
Zadatak 2 · 35 min
K7 i K2: doplatci na ispravnoj osnovici
- Vaš rezultat
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- Dokument
- K2, K4 material price, time per m²
- U ERP-u
- Bill of Quantities
Price the change
Zadatak 3 · 40 min
Zahtjev za dodatne troškove prema ÖNORM B 2110
- Vaš rezultat
- New unit price and the additional cost, filed as a claim
- Dokument
- The site supervisor's (ÖBA) order and the tender price basis
- U ERP-u
- Variations
Invoice
Zadatak 4 · 40 min
Privremena situacija sa zadržanim iznosom za pokriće
- Vaš rezultat
- Interim invoice 1 and the amount payable
- Dokument
- Measured progress and the contract terms
- U ERP-u
- Contracts
Invoice
Zadatak 5 · 40 min
Završna situacija i zadržani iznos za jamstveni rok
- Vaš rezultat
- Final invoice, warranty retention and the remaining payment
- Dokument
- Contract sum, agreed claim, interim payment
- U ERP-u
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.