Introduktion till kursen · 3 min
Kalkylering enligt ÖNORM B 2061: K3, K7 och ett krav på merkostnader
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
Fiktivt projekt- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- Arbete i ERP
- 5 uppgifter, cirka 3 h 5 min
Vem lämnar vad till vem
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Kommer till dig
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage linesUppgift 1
- Wall item 03.01 without a priceUppgift 2
- Contract terms for the retentionsUppgift 4
- ÖBASite supervision, orders and checks
- Order for sound-insulating wallsUppgift 3
- Measured progress to end of AugustUppgift 4
Går från dig
- Hourly rate on K3 and wage lines in the billUppgift 1
- K7 price with the surcharges on K2Uppgift 2
- Additional-cost claim (Nachtrag)Uppgift 3
- Interim invoice (Abschlagsrechnung) with cover retentionUppgift 4
- Final invoice (Schlussrechnung) with warranty retentionUppgift 5
Din väg genom projektet
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
Uppgift 1 · 30 min
K3: arbetslagets timkostnad
- Du tar fram
- Hourly rate of the crew from K3, entered on the wage lines
- Dokument
- K3 inputs and the bill (LV)
- I ERP
- Bill of Quantities
Build the price
Uppgift 2 · 35 min
K7 och K2: påslag på rätt underlag
- Du tar fram
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- Dokument
- K2, K4 material price, time per m²
- I ERP
- Bill of Quantities
Price the change
Uppgift 3 · 40 min
Krav på merkostnader (Mehrkostenforderung) enligt ÖNORM B 2110
- Du tar fram
- New unit price and the additional cost, filed as a claim
- Dokument
- The site supervisor's (ÖBA) order and the tender price basis
- I ERP
- Variations
Invoice
Uppgift 4 · 40 min
A conto-faktura (Abschlagsrechnung) med täckningsinnehåll
- Du tar fram
- Interim invoice 1 and the amount payable
- Dokument
- Measured progress and the contract terms
- I ERP
- Contracts
Invoice
Uppgift 5 · 40 min
Slutfaktura och garantiinnehåll (Haftrücklass)
- Du tar fram
- Final invoice, warranty retention and the remaining payment
- Dokument
- Contract sum, agreed claim, interim payment
- I ERP
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
Blått är det uppgiften lägger till; grått följer med från tidigare.
Kort sagt. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.