Κοστολόγηση με ÖNORM B 2061: K3, K7 και αξίωση για πρόσθετο κόστος
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
Φανταστικό έργο- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- Εργασία στο ERP
- 5 εργασίες, περίπου 3 ώ. 5 λ.
Ποιος δίνει τι σε ποιον
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Έρχεται σε εσάς
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage linesΕργασία 1
- Wall item 03.01 without a priceΕργασία 2
- Contract terms for the retentionsΕργασία 4
- ÖBASite supervision, orders and checks
- Order for sound-insulating wallsΕργασία 3
- Measured progress to end of AugustΕργασία 4
Φεύγει από εσάς
- Hourly rate on K3 and wage lines in the billΕργασία 1
- K7 price with the surcharges on K2Εργασία 2
- Additional-cost claim (Nachtrag)Εργασία 3
- Interim invoice (Abschlagsrechnung) with cover retentionΕργασία 4
- Final invoice (Schlussrechnung) with warranty retentionΕργασία 5
Η διαδρομή σας στο έργο
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
Εργασία 1 · 30 λ.
K3: το ωρομίσθιο της ομάδας
- Παράγετε
- Hourly rate of the crew from K3, entered on the wage lines
- Έγγραφο
- K3 inputs and the bill (LV)
- Στο ERP
- Bill of Quantities
Build the price
Εργασία 2 · 35 λ.
K7 και K2: προσαυξήσεις στη σωστή βάση
- Παράγετε
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- Έγγραφο
- K2, K4 material price, time per m²
- Στο ERP
- Bill of Quantities
Price the change
Εργασία 3 · 40 λ.
Αξίωση για πρόσθετο κόστος βάσει ÖNORM B 2110
- Παράγετε
- New unit price and the additional cost, filed as a claim
- Έγγραφο
- The site supervisor's (ÖBA) order and the tender price basis
- Στο ERP
- Variations
Invoice
Εργασία 4 · 40 λ.
Ενδιάμεσος λογαριασμός με παρακράτηση κάλυψης
- Παράγετε
- Interim invoice 1 and the amount payable
- Έγγραφο
- Measured progress and the contract terms
- Στο ERP
- Contracts
Invoice
Εργασία 5 · 40 λ.
Τελικός λογαριασμός και παρακράτηση ελαττωμάτων
- Παράγετε
- Final invoice, warranty retention and the remaining payment
- Έγγραφο
- Contract sum, agreed claim, interim payment
- Στο ERP
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
Με μπλε ό,τι προσθέτει η εργασία· με γκρι ό,τι έρχεται από πριν.
Με λίγα λόγια. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.