Въведение в курса · 3 мин
Остойностяване по ÖNORM B 2061: K3, K7 и искане за допълнителни разходи
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
Измислен проект- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- Работа в ERP
- Задачи: 5, около 3 ч 5 мин
Кой какво предава на кого
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Идва при вас
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage linesЗадача 1
- Wall item 03.01 without a priceЗадача 2
- Contract terms for the retentionsЗадача 4
- ÖBASite supervision, orders and checks
- Order for sound-insulating wallsЗадача 3
- Measured progress to end of AugustЗадача 4
Тръгва от вас
- Hourly rate on K3 and wage lines in the billЗадача 1
- K7 price with the surcharges on K2Задача 2
- Additional-cost claim (Nachtrag)Задача 3
- Interim invoice (Abschlagsrechnung) with cover retentionЗадача 4
- Final invoice (Schlussrechnung) with warranty retentionЗадача 5
Вашият път през проекта
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
Задача 1 · 30 мин
K3: часовата ставка на бригадата
- Вашият резултат
- Hourly rate of the crew from K3, entered on the wage lines
- Документ
- K3 inputs and the bill (LV)
- В ERP
- Bill of Quantities
Build the price
Задача 2 · 35 мин
K7 и K2: надценки върху правилната база
- Вашият резултат
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- Документ
- K2, K4 material price, time per m²
- В ERP
- Bill of Quantities
Price the change
Задача 3 · 40 мин
Искане за допълнителни разходи по ÖNORM B 2110
- Вашият резултат
- New unit price and the additional cost, filed as a claim
- Документ
- The site supervisor's (ÖBA) order and the tender price basis
- В ERP
- Variations
Invoice
Задача 4 · 40 мин
Междинна фактура със задържане за покритие
- Вашият резултат
- Interim invoice 1 and the amount payable
- Документ
- Measured progress and the contract terms
- В ERP
- Contracts
Invoice
Задача 5 · 40 мин
Крайна фактура и задържане за дефекти
- Вашият резултат
- Final invoice, warranty retention and the remaining payment
- Документ
- Contract sum, agreed claim, interim payment
- В ERP
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.
Накратко. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.