Calculeren volgens ÖNORM B 2061: K3, K7 en een claim voor meerkosten

You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.

Start opdracht 1

A multi-storey concrete frame under construction against a blue sky, with timber formwork and an orange scaffold platform on the upper floor, scaffolding below and glazed openings on the right.Fictief project
Volksschule Lindenau, ZubauPrimary school extension · concrete frame with formwork
Building
School extension with two classrooms and a group room, brick walls and concrete slab
Contract
Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
Calculation
ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
Werk in de ERP
5 opdrachten, ongeveer 3 u 5 min

Wie geeft wat aan wie

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Komt bij u

  • The municipalityClient (Auftraggeberin), pays
    • Bill of quantities (LV) with unpriced wage linesOpdracht 1
    • Wall item 03.01 without a priceOpdracht 2
    • Contract terms for the retentionsOpdracht 4
  • ÖBASite supervision, orders and checks
    • Order for sound-insulating wallsOpdracht 3
    • Measured progress to end of AugustOpdracht 4
UKalkulant, contractor

Gaat van u uit

    • Hourly rate on K3 and wage lines in the billOpdracht 1
    • K7 price with the surcharges on K2Opdracht 2
    • Additional-cost claim (Nachtrag)Opdracht 3
    ÖBAReviews the claim and the invoices
    • Interim invoice (Abschlagsrechnung) with cover retentionOpdracht 4
    • Final invoice (Schlussrechnung) with warranty retentionOpdracht 5
    The municipalityReceives the invoices

Uw route door het project

Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.

  1. Build the price

    Opdracht 1 · 30 min

    K3: het uurtarief van de ploeg

    U levert
    Hourly rate of the crew from K3, entered on the wage lines
    Document
    K3 inputs and the bill (LV)
    In de ERP
    Bill of Quantities
  2. Build the price

    Opdracht 2 · 35 min

    K7 en K2: opslagen op de juiste grondslag

    U levert
    K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
    Document
    K2, K4 material price, time per m²
    In de ERP
    Bill of Quantities
  3. Price the change

    Opdracht 3 · 40 min

    Claim voor meerkosten volgens ÖNORM B 2110

    U levert
    New unit price and the additional cost, filed as a claim
    Document
    The site supervisor's (ÖBA) order and the tender price basis
    In de ERP
    Variations
  4. Invoice

    Opdracht 4 · 40 min

    Termijnfactuur met dekkingsinhouding

    U levert
    Interim invoice 1 and the amount payable
    Document
    Measured progress and the contract terms
    In de ERP
    Contracts
  5. Invoice

    Opdracht 5 · 40 min

    Eindfactuur en garantie-inhouding

    U levert
    Final invoice, warranty retention and the remaining payment
    Document
    Contract sum, agreed claim, interim payment
    In de ERP
    Contracts

From a wage to the final payment

Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.

Site costsEmployer's charges on the wageDaily allowance, no chargesWage with overpayment and allowances
Opdracht 1K3: the crew's hourly costThe collective-agreement wage, then allowances, then the employer's charges on the wage subject to charges, then site costs, built up line by line.
Material from K4, loss includedRisk and profitFinancingOverheads (GGK)Hourly cost from K3
Opdracht 2K2 and K7: surcharges in orderOverheads, financing, risk and profit are applied one after another, each on the sum so far. Added side by side on the base, they come out short.
Supplier's higher price todayMaterial at the tender price listLabour at the tender wage price
Opdracht 3Additional-cost claimThe new price is built from the tender's price basis, not from today's market. Where the bill has no equal item, a comparable one gives the time.
Claim, still in reviewCover retentionNet amount payable
Opdracht 4Interim invoiceMeasured progress at contract prices. The cover retention, a share held back as security, is taken from the net invoice. A claim still under review stays out.
Warranty retention (Haftrücklass)Paid on interim invoiceRemaining payment
Opdracht 5Final invoiceContract sum plus the agreed claim, less the interim payment. The warranty retention comes from the final invoice amount, and the cover retention is released against it.

Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.

Kort gezegd. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.