ÖNORM B 2061 бойынша смета жасау: K3, K7 және қосымша шығындарға талап
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
Ойдан шығарылған жоба- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- ERP-дегі жұмыс
- Тапсырмалар: 5, шамамен 3 сағ 5 мин
Кім кімге не береді
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Сізге келеді
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage lines1-тапсырма
- Wall item 03.01 without a price2-тапсырма
- Contract terms for the retentions4-тапсырма
- ÖBASite supervision, orders and checks
- Order for sound-insulating walls3-тапсырма
- Measured progress to end of August4-тапсырма
Сізден кетеді
- Hourly rate on K3 and wage lines in the bill1-тапсырма
- K7 price with the surcharges on K22-тапсырма
- Additional-cost claim (Nachtrag)3-тапсырма
- Interim invoice (Abschlagsrechnung) with cover retention4-тапсырма
- Final invoice (Schlussrechnung) with warranty retention5-тапсырма
Жоба бойынша жолыңыз
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
1-тапсырма · 30 мин
K3: бригаданың сағаттық бағасы
- Нәтиже
- Hourly rate of the crew from K3, entered on the wage lines
- Құжат
- K3 inputs and the bill (LV)
- ERP-де
- Bill of Quantities
Build the price
2-тапсырма · 35 мин
K7 және K2: үстемелер дұрыс негізде
- Нәтиже
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- Құжат
- K2, K4 material price, time per m²
- ERP-де
- Bill of Quantities
Price the change
3-тапсырма · 40 мин
ÖNORM B 2110 бойынша қосымша шығындарға талап
- Нәтиже
- New unit price and the additional cost, filed as a claim
- Құжат
- The site supervisor's (ÖBA) order and the tender price basis
- ERP-де
- Variations
Invoice
4-тапсырма · 40 мин
Жабу ұстауымен аралық шот
- Нәтиже
- Interim invoice 1 and the amount payable
- Құжат
- Measured progress and the contract terms
- ERP-де
- Contracts
Invoice
5-тапсырма · 40 мин
Қорытынды шот және ақау ұстауы
- Нәтиже
- Final invoice, warranty retention and the remaining payment
- Құжат
- Contract sum, agreed claim, interim payment
- ERP-де
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
Көкпен — тапсырма қосатын бөлік; сұрмен — алдыңғы қадамнан келгені.
Қысқаша. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.