Course introduction · 3 min
Estimating under ÖNORM B 2061: K3, K7 and a claim for extra costs
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
Fictional project- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- Work in the ERP
- 5 tasks, about 3 h 5 min
Who hands what to whom
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Comes to you
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage linesTask 1
- Wall item 03.01 without a priceTask 2
- Contract terms for the retentionsTask 4
- ÖBASite supervision, orders and checks
- Order for sound-insulating wallsTask 3
- Measured progress to end of AugustTask 4
Goes from you
- Hourly rate on K3 and wage lines in the billTask 1
- K7 price with the surcharges on K2Task 2
- Additional-cost claim (Nachtrag)Task 3
- Interim invoice (Abschlagsrechnung) with cover retentionTask 4
- Final invoice (Schlussrechnung) with warranty retentionTask 5
Your route through the job
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
Task 1 · 30 min
K3: the crew's hourly rate
- You produce
- Hourly rate of the crew from K3, entered on the wage lines
- Document
- K3 inputs and the bill (LV)
- In the ERP
- Bill of Quantities
Build the price
Task 2 · 35 min
K7 and K2: markups on the right base
- You produce
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- Document
- K2, K4 material price, time per m²
- In the ERP
- Bill of Quantities
Price the change
Task 3 · 40 min
Claim for extra costs under ÖNORM B 2110
- You produce
- New unit price and the additional cost, filed as a claim
- Document
- The site supervisor's (ÖBA) order and the tender price basis
- In the ERP
- Variations
Invoice
Task 4 · 40 min
Interim invoice with cover retention
- You produce
- Interim invoice 1 and the amount payable
- Document
- Measured progress and the contract terms
- In the ERP
- Contracts
Invoice
Task 5 · 40 min
Final invoice and defects retention
- You produce
- Final invoice, warranty retention and the remaining payment
- Document
- Contract sum, agreed claim, interim payment
- In the ERP
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
Blue is what the task adds; grey is carried over from before.
In short. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.