Panimula ng kurso · 3 min
Pag-estimate ayon sa ÖNORM B 2061: K3, K7 at claim para sa dagdag na gastos
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
Kathang-isip na proyekto- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- Trabaho sa ERP
- 5 gawain, mga 3 oras 5 min
Sino ang nagbibigay ng ano kanino
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dumarating sa iyo
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage linesGawain 1
- Wall item 03.01 without a priceGawain 2
- Contract terms for the retentionsGawain 4
- ÖBASite supervision, orders and checks
- Order for sound-insulating wallsGawain 3
- Measured progress to end of AugustGawain 4
Lumalabas sa iyo
- Hourly rate on K3 and wage lines in the billGawain 1
- K7 price with the surcharges on K2Gawain 2
- Additional-cost claim (Nachtrag)Gawain 3
- Interim invoice (Abschlagsrechnung) with cover retentionGawain 4
- Final invoice (Schlussrechnung) with warranty retentionGawain 5
Ang ruta mo sa proyekto
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
Gawain 1 · 30 min
K3: hourly rate ng crew
- Ang gagawin mo
- Hourly rate of the crew from K3, entered on the wage lines
- Dokumento
- K3 inputs and the bill (LV)
- Sa ERP
- Bill of Quantities
Build the price
Gawain 2 · 35 min
K7 at K2: mga markup sa tamang base
- Ang gagawin mo
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- Dokumento
- K2, K4 material price, time per m²
- Sa ERP
- Bill of Quantities
Price the change
Gawain 3 · 40 min
Claim para sa dagdag na gastos ayon sa ÖNORM B 2110
- Ang gagawin mo
- New unit price and the additional cost, filed as a claim
- Dokumento
- The site supervisor's (ÖBA) order and the tender price basis
- Sa ERP
- Variations
Invoice
Gawain 4 · 40 min
Interim invoice na may cover retention
- Ang gagawin mo
- Interim invoice 1 and the amount payable
- Dokumento
- Measured progress and the contract terms
- Sa ERP
- Contracts
Invoice
Gawain 5 · 40 min
Final invoice at defects retention
- Ang gagawin mo
- Final invoice, warranty retention and the remaining payment
- Dokumento
- Contract sum, agreed claim, interim payment
- Sa ERP
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.
Sa madaling salita. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.