Kursuse sissejuhatus · 3 min
Kalkuleerimine ÖNORM B 2061 järgi: K3, K7 ja lisakulude nõue
You are the estimator (Kalkulant) for the builder of a primary school extension, a public contract. In Austria a public client can ask how every price was built, so prices are worked out on standard forms. In five tasks you build the crew's hourly cost on form K3 and the price of one item on form K7, price an ordered change as an additional-cost claim, and invoice the job from the first interim bill to the final one.
Väljamõeldud projekt- Building
- School extension with two classrooms and a group room, brick walls and concrete slab
- Contract
- Unit-price contract under ÖNORM B 2110 (paid for quantities built), awarded under BVergG 2018, client: a market town (Marktgemeinde)
- Calculation
- ÖNORM B 2061 price forms: K3 (labour rate), K7 (item price), K2 (surcharges)
- Töö ERP-s
- Ülesandeid 5, umbes 3 h 5 min
Kes annab kellele mida
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tuleb sinule
- The municipalityClient (Auftraggeberin), pays
- Bill of quantities (LV) with unpriced wage linesÜlesanne 1
- Wall item 03.01 without a priceÜlesanne 2
- Contract terms for the retentionsÜlesanne 4
- ÖBASite supervision, orders and checks
- Order for sound-insulating wallsÜlesanne 3
- Measured progress to end of AugustÜlesanne 4
Läheb sinult
- Hourly rate on K3 and wage lines in the billÜlesanne 1
- K7 price with the surcharges on K2Ülesanne 2
- Additional-cost claim (Nachtrag)Ülesanne 3
- Interim invoice (Abschlagsrechnung) with cover retentionÜlesanne 4
- Final invoice (Schlussrechnung) with warranty retentionÜlesanne 5
Sinu tee läbi projekti
Two tasks build the price, one prices a change on the same basis, two invoice the work. Start with task 1: in the Bill of Quantities you build the crew's hourly rate on K3 and enter it on the wage lines.
Build the price
Ülesanne 1 · 30 min
K3: brigaadi tunnihind
- Sinu tulemus
- Hourly rate of the crew from K3, entered on the wage lines
- Dokument
- K3 inputs and the bill (LV)
- ERP-s
- Bill of Quantities
Build the price
Ülesanne 2 · 35 min
K7 ja K2: juurdehindlused õigel alusel
- Sinu tulemus
- K2 surcharges as four lines, the K7 price of wall 03.01, and the shortfall if K2 is simply added
- Dokument
- K2, K4 material price, time per m²
- ERP-s
- Bill of Quantities
Price the change
Ülesanne 3 · 40 min
Lisakulude nõue ÖNORM B 2110 järgi
- Sinu tulemus
- New unit price and the additional cost, filed as a claim
- Dokument
- The site supervisor's (ÖBA) order and the tender price basis
- ERP-s
- Variations
Invoice
Ülesanne 4 · 40 min
Vahearve katteperetisega
- Sinu tulemus
- Interim invoice 1 and the amount payable
- Dokument
- Measured progress and the contract terms
- ERP-s
- Contracts
Invoice
Ülesanne 5 · 40 min
Lõpparve ja garantiiperetis
- Sinu tulemus
- Final invoice, warranty retention and the remaining payment
- Dokument
- Contract sum, agreed claim, interim payment
- ERP-s
- Contracts
From a wage to the final payment
Each step builds on the price before it. In the first three, the question is the base a surcharge is applied to. In the last two, it is what the retention is taken from.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Each surcharge goes on the sum before it. Price a change from the tender basis. Take each retention from the base the contract names.